An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Fremington Army Camp – Contamination Concerns June 2016 Andy Cole – Environmental Protection Service Lead

  2. Fremington Army Camp – Regulatory Agencies Roles • North Devon Council • planning • statutory nuisance • Environment Agency • regulation of waste management activities • Health and Safety Executive • regulation of health and safety aspects of construction activities (Healthy and Safety at Work Act 1974) • implications of the construction activities on site on developers employees and other persons

  3. Planning and Contaminated Land • Underpinning Concept of Pollutant Linkages • Phase I / Conceptual Site Model • Phase II / Remediation Method Statement • Verification

  4. Fremington Army Camp - Planning • Planning application received by North Devon Council • Environmental Health and Housing Services statutory consultee –recommended conditions were placed on any decision to be issued – including contaminated land • Committee decision to refuse application - based on issues surrounding the access road and overall character of the development • Appeal hearing April 2013 • Permission granted by Planning Inspector, with conditions

  5. Fremington Army Camp – Contaminated Land • C Land conditions consistent with approach outlined previously – and representing best practice • Phase I and Phase II reports submitted to, and accepted by The Council • Reports identified all contaminants of potential concern. • Extensive sampling and analysis for wide range of parameters – including asbestos – no contaminants present at a level which would represent a risk to Public Health

  6. Fremington Army Camp – Contaminated Land • All reviewed by suitably qualified and experienced EH&HS Officers, and deemed as being acceptable • Officers await submission of verification report which will be reviewed once received once all the works have been completed • Questions ?

  7. Fremington Army Camp – Complaints • Complaints received Winter 2015 concerning : • asbestos having been found on site • the presence of specialist asbestos removal contractors on site • un-sheeted lorries taking material to / from site • imported material being used as topsoil, coming from a contaminated site

  8. Fremington Army Camp – Complaints • Investigations undertaken by Officers confirmed that: • asbestos had been found on site – as acknowledged in reports • developers commissioned full time services of asbestos removal contractors on site, to enable them to promptly deal properly with any asbestos found • asbestos contaminated material was being dealt with appropriately on site • imported topsoil material had not come from a contaminated site

  9. Fremington Army Camp – Complaint s • Allegations received in May 2016 that: • asbestos contaminated material had been transported from Fremington site to the Anchorwood Bank (AWB) development site in un-sheeted lorries

  10. Fremington Army Camp – Complaints • Investigations by Officers confirm that : • AWB was using material from the Fremington site • routine compliance sampling at AWB of material received from Fremington confirmed loose fibres to be present - further analysis confirmed no asbestos present above the acceptable threshold limit of 0.001% • routine compliance sampling of material to be exported – undertaken on site at Fremington - also confirmed loose fibres being present - further analysis confirmed presence of asbestos in 1 sample - at a level of 0.0016 %

  11. Fremington Army Camp – Complaint s • AWB subsequently took the decision to stop importing this material • material received at AWB was in un-sheeted lorries – but did not contain asbestos above the threshold limit – as such the risk to public health from material which had been transported is insignificant • there is currently no formal requirement for material arriving / leaving the Fremington site to be sheeted. The developers had opted NOT to implement their consultants recommendation that sheeted vehicles should be used • Questions ?

  12. Fremington Army Camp – EA / HSE • Environment Agency have undertaken investigations into waste acceptance procedures at AWB – satisfied these procedures are effective • Health and Safety Executive – been advised of recent allegations - as North Devon Council are investigating they do not intend to investigate these specific allegations at this stage

  13. Fremington Army Camp – The Future • What happens next ? • developers at Fremington are working on a Materials Management Plan for this site • this will enable materials on site to be categorised and provide further reassurance / evidence to regulators and community that materials continue to be managed correctly and safely • the site Construction Environment Management Plan shall be amended to include a commitment that sheeted lorries will be used where applicable, to the future

  14. Fremington Army Camp – The Future • What happens next ? • North Devon Council is committed to • providing resource to ensure ongoing proactive regulation of the site, to ensure relevant actions are implemented to it’s satisfaction • ensuring that ongoing development of the site continues to be undertaken in a way which will minimise any perceived associated public health risks • continuing to investigate new allegations

  15. Fremington Army Camp – The Future • New complaints re environmental protection related planning issues or statutory nuisance : • 01271 388344 • andy.cole@northdevon.gov.uk • Waste management / health and safety : • Health and Safety Executive – ww.hse.gov.uk • Environment Agency – enquiries@environment-agency.gov.uk or 03708 506506