An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. NEH Safety Systems Enzo Carrone June 30th , 2009

  2. PPS and BCS Status • Both systems are currently ready for safe operation to the FEE • PPS successfully certified (IAT) on June 24-26; • BCS components certified on June 26. • Hutch systems • HPS will be ready by the end of July.

  3. Safety Systems Section • PPS and BCS Systems combined into a single Section. • Full-time QC Group Leader (M. Saleski). • Manages Review Process. • Oversees Engineering Change Order Process. • Full-time Documentation Manager (S. Starner). • Documentation system compliant to DOE Order 414.1C and ISO 9001-2000.

  4. Safety Systems Section Documentation Structure

  5. Safety Systems QA • Subject to a new Engineering Change Order (ECO) process • Better tracking of requirements, specifications, reviews (peer and formal), and system documentation. • New project QA approach • Bench and pre-IAT field test of system software • Acceptance tests performed for complex SLAC-built assemblies (such at stoppers) • Cold and energized checkout of installed hardware • Und Complex lessons learned with subcontractors • Formal IAT reviews with stakeholders • Overall, better management of schedule • Indirectly affects quality

  6. Documentation Control • A single on line repository is available for all released documents. • Formal Documentation Control is in place. • Measures taken to regulate the Preparation, Change, Withdrawal, Review, Approval, Release, Distribution, Access, Availability, Storage, Disposal of documents. • Document management Plan, Document Change Control Procedure, design Review Plan, Drawing Management Procedure, Engineering Change Order Procedure.

  7. Configuration Control Elements • Prevention of Unintended Change • Physical Security of System • Labeling • Training • Control of Intended Change • Work Planning (adequate review of design) • Work Authorization (RSWCF) • Verification of Work (RSWCF) • Periodic Confirmation of System Integrity • Routine testing and inspections

  8. Configuration Management Documentation • Document Management Plan • Document Change Control Procedure • Document Change Order • Design Review Plan • Software Configuration Management • Engineering Change Order Procedure • Engineering Change Order • Drawing Management Procedure

  9. Software Configuration Management Support • Software versions are checked during annual certification. • Written procedures exist for extracting PPS code from CVS and for uploading it to PLCs. • A documented training program tracks personnel PLC qualifications in the Section.

  10. Software Configuration Management Procedure • PPS Software is stored in a dedicated PPS repository. • Released software always has “N.0.0” version tag. • Documented software bench testing is performed prior to deployment.

  11. Software Configuration Control Issues • Program Security: • All communication to the safety-critical PLCs is through TCP/IP to ‘buffer’ Allen-Bradley PLC, then via DeviceNet (serial data communication). • Safety-critical program ‘smart card’ cannot be written to while in the PLC • Communication from the safety-critical PLCs is through DeviceNet to ‘buffer’ Allen-Bradley PLC and output to control system via TCP/IP • Network Access Security: • Hardwire Enable from MCC required • Only specific IP addresses are allowed to issue PPS commands • Physical Access Security: • PLCs and DeviceNet are inside locked racks.

  12. Software Version Management • Version Management: • Software versions are checked during annual certification • Written procedures Exist for extracting PPS code from CVS and uploading it to PLCs • A documented training program tracks personnel PLC qualifications in the Section

  13. Implementation, Operations, and Maintenance

  14. Proposed PLC PPS ‘Dev and Rev’

  15. Established SSS ECO • Emphasis on review and development documentation; • Enables a project management approach; • Collects development and review docs for auditability.

  16. FEE/NEH PPS Checkouts • Cold Checkout • Verifies Hardware and Cable Plant is installed and wired correctly • Verifies No Ground Shorts in the Cable Plant • EEIP Hardware and Racks • Hot Checkout • Verifies Functionality of Hardware, Devices, and PLCs • Hi-Pot Cable Plant

  17. Review Status • Final Design Review #2 (April 22, 2009) • Initial Acceptance Test Review (internal and external) • Starting this week.

  18. Major Review to Date LCLS SCR: May 31st 2007 [Bong, Stefan, Horton, Hastings] LCLS PDR: Feb 29th 2008 [Lessard, Tompkins, Schmerge, Anthony] LCLS FDR: Oct 22nd 2008 [Anthony, Mueller(LBNL), Lessard] RSC: Oct 31st 2008 LCLS FDR2: Apr 22nd 2009 [Perry Anthony, Zoe Van Hoover, Luc Lessard, Paul Miller, Robert Mueller, Mike Woods] PPS Review Status for FEE & NEH

  19. PPS FEE Schedule

  20. FEE/NEH Schedule

  21. Conclusions • PPS/BCS has a Quality Assurance model in place; • LCLS management is aware of the Safety Systems process and supports it throughout the project lifecycle (from conception to certification); • LCLS, Operations, Radiation Physics are heavily involved in all review phases from early on (from requirements/specifications to user manual).