Environmental Impact Assessment (EIA) in the Philippines: Roads Taken, Lessons Learned for Mining Projects By: Catalon, Ma. Lourdes Nanette D. and Manaog, Melanie D. 27 th IAIA Annual Conference, Seoul, Korea June 2007. Map of Southeast Asia.

kaitlinp
Download Presentation

27 th IAIA Annual Conference, Seoul, Korea June 2007

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Environmental Impact Assessment (EIA) in the Philippines: Roads Taken, Lessons Learned for Mining Projects By: Catalon, Ma. Lourdes Nanette D. and Manaog, Melanie D. 27th IAIA Annual Conference, Seoul, Korea June 2007

  2. Map of Southeast Asia 27th IAIA Annual Conference, Seoul, Korea, June 2007

  3. Areas in the Philippines with Potential for Metallic Mineralization 27th IAIA Annual Conference, Seoul, Korea, June 2007

  4. Didipio Gold Copper Project Masbate Gold Project RTNMC HPP Line 1 CBNC HPP Line 2 Areas in the Philippines with Potential for Metallic Mineralization 27th IAIA Annual Conference, Seoul, Korea, June 2007

  5. Mineral Wealth of the Philippines: • Top 10 producer of copper, chromite, gold and nickel in the world; • 30% of total land area or 10M hectares has mineral deposits; • 7B metric tons or metallic reserves gold, copper, nickel, chromite; • Gold - 1B tons reserves • Copper - 5B tons reserves 27th IAIA Annual Conference, Seoul, Korea, June 2007

  6. Contribution of the Mining Industry to the Philippine Economy (2003): • Production value: P41.5 Billion • Value-Added Contribution: P17.9 Billion or 1.5 % of Philippine GDP • Exports: US$638 million or 1.8 % of total Philippine Exports • Approved FDI in mining: P855 Million 27th IAIA Annual Conference, Seoul, Korea, June 2007

  7. Contribution of the Mining Industry to the Philippine Economy (2003): • Employment: 104,000 • Wages and benefits: P4 to 5 Billion • Taxes and fees: P2 Billion • Multiplier effect: For each mining job, 4 to 10 allied jobs created upstream and downstream 27th IAIA Annual Conference, Seoul, Korea, June 2007

  8. Regulations Covering Mining Projects in the Philippines: • PD 1151 - Philippine Environmental Policy; • PD 1586 - Philippine EIS System; • RA 7942 - Philippine Mining Act • EO 270 - Minerals Action Plan 27th IAIA Annual Conference, Seoul, Korea, June 2007

  9. The EIA Process in the Philippines: 1. Scoping Process 2. EIA Study 27th IAIA Annual Conference, Seoul, Korea, June 2007

  10. The EIA Process in the Philippines: 3. Review Process 27th IAIA Annual Conference, Seoul, Korea, June 2007

  11. Other Regulations Covering Development Projects in the Philippines: • RA 8749 - Clean Air Act • RA 9275 - Clean Water Act • RA 6969 - An Act to Control Toxic Substances and Hazardous and Nuclear Wastes • RA 9003 - Ecological Solid Waste Management Act • RA 8371 - Indigenous Peoples Republic Act 27th IAIA Annual Conference, Seoul, Korea, June 2007

  12. ELECTROSTATIC PRECIPITATOR BOILER STACK STEAM TURBINE GENERATOR Rio Tuba Nickel Mining Corporation – HPP Line 1 • 1996 EIA for the 990 ha MPSA Application • 2000 EIA for the HPP Line 1 • Located in the Province of Palawan; need to secure PCSD Clearance • Underwent 2 separate EIS Reviews 27th IAIA Annual Conference, Seoul, Korea, June 2007

  13. Rio Tuba Nickel Mining Corporation – HPP Line 1 27th IAIA Annual Conference, Seoul, Korea, June 2007

  14. Coral Bay Nickel Corporation – HPP Line 2 • 2006 EIA for the new facilities to double capacity of Line 1 • Required to submit an Environmental Performance Report and Management Plan (EPRMP) • Emphasis on the socio-economic impacts of the project during the review • Less than one month processing time 27th IAIA Annual Conference, Seoul, Korea, June 2007

  15. Coral Bay Nickel Corporation – HPP Line 2 27th IAIA Annual Conference, Seoul, Korea, June 2007

  16. Coral Bay Nickel Corporation – HPP Line 2 Safety Orientation with REVCOM Site Visits Water Quality Monitoring IEC Activities 27th IAIA Annual Conference, Seoul, Korea, June 2007

  17. OceanaGold - Didipio Gold/Copper Mining Project • 1994 EIA and amendments in 1999 and 2004 • One of the 2 mining projects awarded with a FTAA • Conducted a 5-year social preparation program including IEC and SocDev Programs 27th IAIA Annual Conference, Seoul, Korea, June 2007

  18. OceanaGold - Didipio Gold/Copper Mining Project 27th IAIA Annual Conference, Seoul, Korea, June 2007

  19. Filminera Resources Corp. - Masbate Gold Project • 1997 EIA to reopen gold mine under the ACMDC • Old operations did not undergo the EIA process • 90% social acceptability • Fast EIA Review and Processing (2 months) 27th IAIA Annual Conference, Seoul, Korea, June 2007

  20. Filminera Resources Corp. - Masbate Gold Project Archaeological Assessment Team briefing with LGU 27th IAIA Annual Conference, Seoul, Korea, June 2007

  21. Lessons Learned: • Identify who the actual stakeholders are • Increase awareness of stakeholders and transparency of project proponents. • Process document all activities • Best practice environmental practices and social development programs • Community Relations 27th IAIA Annual Conference, Seoul, Korea, June 2007

  22. Lessons Learned: Identify who the actual stakeholders are • Recognize the cultural distinctiveness of each identified stakeholder group • Consider IPs’ cultural uniqueness and their precarious situation • Identify stakeholders’ concerns – their apprehensions, their perception, and their fears 27th IAIA Annual Conference, Seoul, Korea, June 2007

  23. Lessons Learned: Increase awareness of stakeholders and transparency of project proponents • Initiate periodic Information, Education, and Communications (IEC) activities • Generate high level of awareness among various stakeholders 27th IAIA Annual Conference, Seoul, Korea, June 2007

  24. Lessons Learned: Process document all activities • IEC, consultations, agreements reached • permanent record which could be used for continuity of discussion with various stakeholders 27th IAIA Annual Conference, Seoul, Korea, June 2007

  25. Lessons Learned: Best practice environmental practices and social development program • Consider & select design, location and development of (project) components that reduce environmental consequences; • Considerable investment on pollution control facilities, environmental management and monitoring programs; • EPEP • CLRF • Social development programs that are responsive to communities’ needs and which consider local participation and the assimilative or absorptive capacity of local communities 27th IAIA Annual Conference, Seoul, Korea, June 2007

  26. Lessons Learned: Community Relations • Seek and maintain healthy relations with host communities & local authorities to ensure coordination • Need to coordinate with affected IP groups & those considered “minority” groups (if any); • Information, Education and Communications (IEC) activities; • Community Relations Office 27th IAIA Annual Conference, Seoul, Korea, June 2007

  27. Conclusion: • Development projects result in changes in the environment and lives and culture of peoples where these are located; • Need for management of impacts to the environment and preparation of project receptors or stakeholders to changes; • In the Philippines, legal framework is in place; • Need for Project owners to understand dynamics involved when proposing mining projects and implement best-practice mining. 27th IAIA Annual Conference, Seoul, Korea, June 2007

  28. Maraming Salamat! Mabuhay Maria Nanette Lourdes D. Catalon & Melanie D. Manaog Gaia South, Inc. 7F Montepino Bldg, Adelandato Cor. Gamboa Sts Legaspi Village 1229 Makati City Philippines Tel. No: +632 8935661 Fax No.: +632 8935657 Email: gaia@info.com.ph cdn3303@yahoo.com melaniemanaog@yahoo.com 27th IAIA Annual Conference, Seoul, Korea, June 2007