Integration and Test. Integration Agenda. Recent Activities Environmental Tests Completed Delivery to Astrotech Probe Processing Fueling Preparations Carrier Processing Probe and Instrument Status Instrument Status and Remaining Items Probe Status and Remaining Items Integration Plan
E N D
Integration Agenda • Recent Activities • Environmental Tests Completed • Delivery to Astrotech • Probe Processing • Fueling Preparations • Carrier Processing • Probe and Instrument Status • Instrument Status and Remaining Items • Probe Status and Remaining Items • Integration Plan • Review Process • RFAs in Work • Reviews Ahead
Environments Magnetics Vibration Acoustics EMC Thermal Vacuum Spin Balance
Probe Processing Delivery to ASO Bolt Cutter Installation Solar Array Illumination Performance Tests
Probe Fueling Preps Vibration Acoustics Spin Balance Dry Weigh & Pressurize Ready for Fuel FM2/FM3 Thermal Vacuum Thermal Vacuum Storage
Carrier Processing PC Unload Vibration Acoustics Spin Balance Ready for Probes Storage SSS Installation
Instrument Status • Instrument Status • Flight Hardware Ready • Flight Software Ready Recent Activities • Performance Test Remaining Items • ESC Verification • SST/ESA Covers • EFI Hats • Contamination Samples
Probe Status • Probe Status • Hardware Complete • Software Complete Recent Activities at ASO • Performance Tests • Solar Array Illumination • RCS Pressurization to 1.1*MEOP • Dry Weigh Remaining Items • Fueling • Flight Plugs • Integrate to PC • Attach Sep System
Integration Flow ASTROTECH and Launch Pad Flow THEMIS Launch 12/08/06 to Shipping from JPL 12/11/06 12/13/06 12/19/06 12/20/06 12/12/06 12/11/06 12/14/06 12/15/06 12/15/06 12/19/06 12/21/06 Install Bolt Cutters, Therm. Closeouts F4-5 RCS MEOP, LPT, S/A Test F2-3 RCS MEOP, LPT, S/A Test 5 Probes plus EGSE, MGSE at ASO F1 RCS MEOP, LPT, S/A Test Unpack, Setup EGSE Move Probes to HPF 12/11/06 Probe Carrier Unpack 12/15/06 PC-VCO Electrical Test 01/13/07 01/09/07 01/11/07 12/22/06 01/08/07 01/10/07 01/12/07 12/23/06 01/03/07 01/05/07 01/02/07 Weigh Wet Probes, Attach Pyro PCA Funct. Spin Balance Christmas Shutdown Probe RCS Electr. Verif. Weigh, Move to Stands Weigh PCA Probe Fueling 12/18/06 Install Sep. Harness 01/03 01/12 Pre-Vos LVRR (KSC) 01/05 MRR (GSFC) 01/12 Media Day 12/19/06 Install SMDC Lines 01/23/07 01/24/07 01/26/07 01/29/07 01/25/07 01/27/07 01/30/07 01/3107 02/01/07 01/22/07 02/02/07 01/15/07 Install Pyro Signal SMDC/ Weigh PCA PCA Mate to 3rd Stage/ Clamp-band Instl PCA Comm Check @ Blockhouse Engr Walk-down/ Trans- port Preps Transport to Pad PCA Functional Reserve 01/23 02/01 MRR (HQ) LSRR (CCAFS) 02/08/07 02/12/07 02/13/07 02/14/07 02/05/07 02/03/07 02/06/07 02/07/07 02/09/07 02/15/07 2nd Stage Fueling, Ordnance Launch Readiness Review Install Fairing Power On & Stray Voltage Launch Launch Rehearsal Prop. Load Prep S/C Functional & RF Test FRR (KSC) 02/12 02/13 LMCM (KSC)
RFAs • RFA Status • Incomplete: 0 • Complete: 308 • Closed: 304 • Total: 308 • Final Four Closure Method • RCS Proof Issue: Expected to Close with Risk Definition • BAU EEPROM Plots Provided were Insufficient to the reviewer but it is no longer practical to obtain better plots. • Energy Balance was Provided using Best Thermal Model at the time. Reviewer repeated request using new mission profile and correlated thermal model. This was delivered in December. • Launch Window Analysis will be reviewed by GSFC by 1/15/07