LRO Integration and Test Joanne Baker GSFC Code 568 August 16-17, 2005
I&T Driving Documents • LRO testing shall be in accordance with the “LRO Verification Plan”, 431-PLAN-000101. • LRO integration and test shall be performed per the “LRO Integration and Test Plan”, 431-PLAN-000100. • LRO launch site activities shall be performed in accordance with the “LRO Launch Site Support Plan”.
I&T Document Tree LRO Mission Requirements Document 431-RQMT-00004 LRO Mission Vehicle Interface Control Doc RLEP Mission Assurance Requirements 430-RQMT-000006 LRO Detailed Mission Requirements (DMR) for the LRO Ground System 431-RQMT-000048 GENERAL ENVIRONMENTAL VERIFICATION STANDARD (GEVS) LRO Electrical Systems Specification 431-ICD-000008 LRO System Safety Plan 431-PLAN-000176 Mechanical Systems Specification 431-RQMT-000012 SC PAIP 431-PLAN-000131 Thermal Systems Specification 431-SPEC-000091 Contamination Control Plan 431-PLAN-000110 LRO Ground System ICD 431-ICD-000049 SC Subsystem & Instr. ICDs / Specifications/ Requirements Rules for the Design, Development, Validation, and Operation Of Flight Systems GSFC-STD-1000 Subsystem & Instr. Interface / Assembly Drawings Observatory Verification Plan & Matrix 431-PLAN-000101
I&T Document Tree – cont. LRO Detailed Mission Requirements (DMR) for the LRO Ground System 431-RQMT-000048 LRO System Safety Plan 431-PLAN-000176 SC PAIP 431-PLAN-000131 Instrument Integration & Test Plans Observatory Verification Plan & Matrix 431-PLAN-000101 Mission Readiness Test Plan 431-PLAN-000079 Contamination Control Plan 431-PLAN-000110 Integration and Test Plan 431-PLAN-000100 Test Plans & Procedures Simulations Handling & Lift Procedures GSE Requirements/ Specification Docs ITOS Procs WOAs Test Results And Reports Verification Matrix
I&T Document Tree – cont. LRO System Safety Plan 431-PLAN-000176 Integration and Test Plan 431-PLAN-000100 LRO MSPSP Launch Site Support Plan Ground Operations Procedures
Orbiter Integration & Test Flow - 1 Flt. PowerSystem Delivery Battery & PSE Plate Integration Flt. C&DH System Delivery C&DH Plate Integration Propulsion Module Delivery Reaction Wheel Integration Upper Structure Integration Battery & PSE Orbiter Integration & Test C&DH Integration & Test PDE Integration & Test RF components Integration & Test Preliminary Bus Functional Testing Bus Mounted Instrument Integration & Test SA and HGA Integration & Test Optical Bench Integration & Test Flat Sat Build Up and Checkout Inst. Interface Check Out W/ Flat Sat OB - Instrument Integration & Alignment Optical Bench Delivery ST & IRU Integration & Alignment
Orbiter Integration & Test Flow - 2 Instrument Functional Tests RF Compatibility Test ACS Polarity Test Time Offset/Drift Test Alignment Baseline LOLA Boresight Alignment LAMP End to End Test CPT S/A and HGA Deployment Tests Jitter Characterization Day In the Life Mission Sims Comm Sys End to End Test
Orbiter Integration & Test Flow - 3 Pre-Environmental Review Sine Vibe W/ Aliveness Acoustics W/ Aliveness Separation/ Shock Test Alignment Check & Functional Test EMC Thermal Vac & Balance Alignment Check Post Environmental CPT Bus & Instrument Special Tests Pre-Ship Activities Ship To KSC Post-Ship Activities Post-Ship Functional or CPT Fueling Final Close Outs Pad Readiness Activities Pad Installation Pad Aliveness Test Spin Balance / Mass Properties Fairing Installation LAUNCH
I&T Verification Summary • Interfaces • Mechanical Integration; Electrical Integration Procedures; Polarity test; Alignment; Spin Balance; Mass Properties • Functionality Hardware • Functional Test; Performance; Time verification; End to End Tests; Deployment Tests • Functionality Software • Day in the Life; Separation timeline; Mission Sims • Environments • Contamination; Jitter Characterization; Sine Vibe; Acoustics; Shock / Separation Test; EMC; Thermal Vac / Balance • Instrument Special Tests (unique configurations) • LOLA: Boresight alignment check; LAMP: End to End Test;
Ground Support Equipment – Orbiter Level • Simulators: Instrument simulators, Spacecraft simulators; Flat Sat • Mechanical GSE • Lift fixtures, handling dolly, turnover fixture, transportation fixture, thermal vac support structure. • C&DH GSE • Front End Processors – S-band & Ka-band • 1553 Bus Monitor • Space Wire Test Rack • Data Storage • Workstations • RF racks & antenna hats • Time test rack • Power GSE • Solar Array Simulator; Battery Simulator; Load Box • ACS GSE • Dynamic Simulator; ACS component stimulators: Star Tracker, IRU • Propulsion module simulator/GSE • Instrument Unique Ground Support Equipment • CRaTER: CO60 source; non-ITOS workstation; Diviner: BCE; LAMP: Vac Ion, Pump, UV light source; LEND: Californium source; LOLA: Laser Test Equipment (BCE), target; LROC: none identified • Contamination • Instrument GN2 purges
I&T Summary • Instrument requirements identified to date and understood. • Most difficult area will be thermal vac test configuration. • Testing may be limited by configuration limitations. • Other I&T requirements are not unique and can be realized. • I&T plan will be in released draft form by mission PDR. • Ready to proceed with preliminary design.