LRO Integration and Test

LRO Integration and Test. Joanne Baker GSFC Code 568 August 16-17, 2005. I&T Driving Documents. LRO testing shall be in accordance with the “LRO Verification Plan”, 431-PLAN-000101. LRO integration and test shall be performed per the “LRO Integration and Test Plan”, 431-PLAN-000100.

Download Presentation

LRO Integration and Test

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. LRO Integration and Test Joanne Baker GSFC Code 568 August 16-17, 2005

  2. I&T Driving Documents • LRO testing shall be in accordance with the “LRO Verification Plan”, 431-PLAN-000101. • LRO integration and test shall be performed per the “LRO Integration and Test Plan”, 431-PLAN-000100. • LRO launch site activities shall be performed in accordance with the “LRO Launch Site Support Plan”.

  3. I&T Document Tree LRO Mission Requirements Document 431-RQMT-00004 LRO Mission Vehicle Interface Control Doc RLEP Mission Assurance Requirements 430-RQMT-000006 LRO Detailed Mission Requirements (DMR) for the LRO Ground System 431-RQMT-000048 GENERAL ENVIRONMENTAL VERIFICATION STANDARD (GEVS) LRO Electrical Systems Specification 431-ICD-000008 LRO System Safety Plan 431-PLAN-000176 Mechanical Systems Specification 431-RQMT-000012 SC PAIP 431-PLAN-000131 Thermal Systems Specification 431-SPEC-000091 Contamination Control Plan 431-PLAN-000110 LRO Ground System ICD 431-ICD-000049 SC Subsystem & Instr. ICDs / Specifications/ Requirements Rules for the Design, Development, Validation, and Operation Of Flight Systems GSFC-STD-1000 Subsystem & Instr. Interface / Assembly Drawings Observatory Verification Plan & Matrix 431-PLAN-000101

  4. I&T Document Tree – cont. LRO Detailed Mission Requirements (DMR) for the LRO Ground System 431-RQMT-000048 LRO System Safety Plan 431-PLAN-000176 SC PAIP 431-PLAN-000131 Instrument Integration & Test Plans Observatory Verification Plan & Matrix 431-PLAN-000101 Mission Readiness Test Plan 431-PLAN-000079 Contamination Control Plan 431-PLAN-000110 Integration and Test Plan 431-PLAN-000100 Test Plans & Procedures Simulations Handling & Lift Procedures GSE Requirements/ Specification Docs ITOS Procs WOAs Test Results And Reports Verification Matrix

  5. I&T Document Tree – cont. LRO System Safety Plan 431-PLAN-000176 Integration and Test Plan 431-PLAN-000100 LRO MSPSP Launch Site Support Plan Ground Operations Procedures

  6. Orbiter Integration & Test Flow - 1 Flt. PowerSystem Delivery Battery & PSE Plate Integration Flt. C&DH System Delivery C&DH Plate Integration Propulsion Module Delivery Reaction Wheel Integration Upper Structure Integration Battery & PSE Orbiter Integration & Test C&DH Integration & Test PDE Integration & Test RF components Integration & Test Preliminary Bus Functional Testing Bus Mounted Instrument Integration & Test SA and HGA Integration & Test Optical Bench Integration & Test Flat Sat Build Up and Checkout Inst. Interface Check Out W/ Flat Sat OB - Instrument Integration & Alignment Optical Bench Delivery ST & IRU Integration & Alignment

  7. Orbiter Integration & Test Flow - 2 Instrument Functional Tests RF Compatibility Test ACS Polarity Test Time Offset/Drift Test Alignment Baseline LOLA Boresight Alignment LAMP End to End Test CPT S/A and HGA Deployment Tests Jitter Characterization Day In the Life Mission Sims Comm Sys End to End Test

  8. Orbiter Integration & Test Flow - 3 Pre-Environmental Review Sine Vibe W/ Aliveness Acoustics W/ Aliveness Separation/ Shock Test Alignment Check & Functional Test EMC Thermal Vac & Balance Alignment Check Post Environmental CPT Bus & Instrument Special Tests Pre-Ship Activities Ship To KSC Post-Ship Activities Post-Ship Functional or CPT Fueling Final Close Outs Pad Readiness Activities Pad Installation Pad Aliveness Test Spin Balance / Mass Properties Fairing Installation LAUNCH

  9. I&T Verification Summary • Interfaces • Mechanical Integration; Electrical Integration Procedures; Polarity test; Alignment; Spin Balance; Mass Properties • Functionality Hardware • Functional Test; Performance; Time verification; End to End Tests; Deployment Tests • Functionality Software • Day in the Life; Separation timeline; Mission Sims • Environments • Contamination; Jitter Characterization; Sine Vibe; Acoustics; Shock / Separation Test; EMC;  Thermal Vac / Balance • Instrument Special Tests (unique configurations) • LOLA: Boresight alignment check; LAMP: End to End Test;

  10. Ground Support Equipment – Orbiter Level • Simulators: Instrument simulators, Spacecraft simulators; Flat Sat • Mechanical GSE • Lift fixtures, handling dolly, turnover fixture, transportation fixture, thermal vac support structure. • C&DH GSE • Front End Processors – S-band & Ka-band • 1553 Bus Monitor • Space Wire Test Rack • Data Storage • Workstations • RF racks & antenna hats • Time test rack • Power GSE • Solar Array Simulator; Battery Simulator; Load Box • ACS GSE • Dynamic Simulator; ACS component stimulators: Star Tracker, IRU • Propulsion module simulator/GSE • Instrument Unique Ground Support Equipment • CRaTER: CO60 source; non-ITOS workstation; Diviner: BCE; LAMP: Vac Ion, Pump, UV light source; LEND: Californium source; LOLA: Laser Test Equipment (BCE), target; LROC: none identified • Contamination • Instrument GN2 purges

  11. I&T Summary • Instrument requirements identified to date and understood. • Most difficult area will be thermal vac test configuration. • Testing may be limited by configuration limitations. • Other I&T requirements are not unique and can be realized. • I&T plan will be in released draft form by mission PDR. • Ready to proceed with preliminary design.