ELECTRICAL INTERCONNECTIONS THE POINT OF VIEW OF A NON REGULATED ACTOR

ELECTRICAL INTERCONNECTIONS THE POINT OF VIEW OF A NON REGULATED ACTOR. François MESLIER Director, Senior Vice President Interconnection Mission, EDF. IFRI Energy Breakfast Roundtable – 6th of July, 2009. EDF strongly in favour of the European electricity market.

kamal-huff
Download Presentation

ELECTRICAL INTERCONNECTIONS THE POINT OF VIEW OF A NON REGULATED ACTOR

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. ELECTRICAL INTERCONNECTIONSTHE POINT OF VIEWOF A NON REGULATED ACTOR François MESLIER Director, Senior Vice President Interconnection Mission, EDF IFRI Energy Breakfast Roundtable – 6th of July, 2009

  2. EDF strongly in favour of the European electricity market • Security, liquidity, fluidity, economy, … • Change of scope for the relevant market • Market opportunities • ….. IFRI Energy Breakfast Roundtable - 6th of July, 2009

  3. 1. Lack of interconnection capacity • Better use of existing infrastructure • Market coupling (Belpex, and extensions) • Coordination between TSOs (Careso, and extensions) • ….. • And necessity of new hardware ! IFRI Energy Breakfast Roundtable - 6th of July, 2009

  4. 1. Lack of interconnection capacity Revenue of auctions in 2008 : 1,7 G€ ! IFRI Energy Breakfast Roundtable - 6th of July, 2009

  5. 1. Lack of interconnection capacity • Need to reinvest these revenues ! • 1,7 G€ / year  37 FR - SP (underground)  188 FR – SP (overhead) • 3rd directive disappointing from this point of view • The regulators (national, ACER ?) to stop this kind of cross subsidy IFRI Energy Breakfast Roundtable - 6th of July, 2009

  6. 2. And it should become worse in the future • Development of wind energy • Renewal of nuclear programs Does the UCTE Transmission Development Plan answer the needs, as they are today, as they will evolve in the future ? IFRI Energy Breakfast Roundtable - 6th of July, 2009

  7. 3. The costs of the new links will probably increase very strongly • FR – SP 80 – 180 M€ overhead 400 – 500 M€ underground • The European Economic Recovery Plan should subsidise up to 220 M€ • More and more Underground Subsideries welcomed ! IFRI Energy Breakfast Roundtable - 6th of July, 2009

  8. 4. Towards subsidies to help underground / under the sea developments • Gas and electricity • Security and peripheral countries and market integration • TEN revision will be a good opportunity IFRI Energy Breakfast Roundtable - 6th of July, 2009

  9. 5. The scene does not change rapidly enough • Yes to merchant lines (ex. : IMERA) • To speed up the process • Yes to open season procedures • To size correctly the interconnections • To share the risks between actors IFRI Energy Breakfast Roundtable - 6th of July, 2009

  10. Let us stop talking about the European electricity market LET US MAKE IT : • Reinvest auction revenues (TSOs, Regulators) • TEN revision (subsidies for gas and electricity) • Merchant lines • Open season IFRI Energy Breakfast Roundtable - 6th of July, 2009

  11. THANK YOU IFRI Energy Breakfast Roundtable - 6th of July, 2009