PPA Solutions Established in Aug 2012: Hugh Mullany and Rory Mullan - Mullany Engineering Consultancy and Mullan Grid What we have been doing? Restructuring Supplier Lite Registrations Reviewing PPA Options Negotiating PPAs for Merchant, REFIT II and REFIT III Review Terms & Conditions of PPAs Audit and review of REFIT I PPAs Setting up Supplier Lite Structures Due Diligence Review SEM prices for Generators Registering Generators for LECs Supporting REFIT audited year-end submissions
Today Current PPA Position of Generators Questions to consider to understand impact of European Target Model on Existing PPAs
The Power Purchase Agreement Supply Co. BILL PPA • Fixed: A fixed rate per MWh, without or without indexation • Pass through: All SEM/REFIT/LEC/GO revenues, less a flat • administration fee or price per MWh traded • Floor with upside, or price guarantee
Types of Generator PPAs Support Scheme PPAs AER Electric Ireland REFIT I & II Any 3rdParty Irish Supplier Supplier Lite Outside Support Scheme PPAs Merchant - market pass through 3rdParty Suppliers Supplier Lite Fixed price with 3rd party supplier Hybrid with 3rd party supplier
Current Market Structure - SEM Supply Co. BILL Supply Co. BILL GENERATION SUPPLY MONEY POWER Single Electricity Market PPA Wind> 10MW Intermediary PPA Outside SEM/ Negative Demand Wind <10 MW
SEM Payments & Charges Supply Co. BILL Supply Co. BILL GENERATION SUPPLY MONEY POWER Single Electricity Market PPA Charges - Energy (SMP) - Capacity - Imperfection - Market Operators Payments - Energy (SMP) - Capacity Wind> 10MW Intermediary PPA Outside SEM/ Negative Demand Wind <10 MW
Benefits of Current SEM Structure • Identical generators producing the same power at the same time receive the same revenues • Shared SMP and Capacity Payment • Transparency of prices • Wind prices are relatively close to average prices • Generators < 10 MW can register as negative demand • Relatively low cost to operate in SEM
New Market Changes • New prices: • Day Ahead • Within-Day • Balancing • Supplier who has bought your power under a PPA can choose how to trade-on your power • That choice impacts how much money your windfarm makes • Choice may be restricted by lack of available counterparty • Identical generators producing the same power at the same time receive revenues based on their trading skill
Impact of new Market on Existing PPAs Support Scheme PPAs - REFIT I & II • Relevant differences in REFIT I & II • The REFIT II reference and technology rate (not including balancing payment) is guaranteed and has to be passed on to the generator • Less potential for market upside in REFIT II • Market Change Clauses in PPAs • Two general types of Market Change Clauses: • Allow mechanical changes, for examples changes in payment timelines • Reopening of price negotiations to allow both parties to maintain commercial positions • If the supplier is making less money trading your power, they may – PPA permitting – seek to change the price under the PPA
Impact of new Market on Existing PPAs Support Scheme PPAs - REFIT I & II - continued • What market prices will be utilised by CER for REFIT? • For forecasts (Day Ahead, Within Day, Balancing) • For reconciliation (REFIT currently tops up any supplier to the guaranteed rates, irrespective of how much or little money the supplier has made selling on your power) • Impact on potential for upside if allowed under the PPA • Impact of changes in PPA on loan agreements • Should also consider impact of new market on project revenues post REFIT term
Impact of new Market on Existing PPAs Outside Support Scheme PPAs • Merchant - market pass through • Term of current PPAs generally end in 2016 or earlier • Availability, structure and price of new PPAs post 2016?? • Fixed price with 3rd party supplier • Depends on Market Change Clauses in PPA • Need to also consider new market’s impact on future project revenues • PPA structure required for repowering?
Impact of new Market on Existing PPAs General • Will there be Capacity Payments & Capacity Charges? • What will market revenues be like in the European Target Model? • Will the choice of when to trade make much of a difference on revenues? • Will <10MW generators still see the benefits of offsetting demand? • Cost of forecasting and trading in the new Market? • Implementing of priority dispatch? • And of course the detail ….
Conclusions • Know Your Own Position • Too early to fully understand potential impact • Need to stay informed • Ensure this sector has a strong voice, individually and collectively