1 / 18

1/4/2020

1/4/2020. AASHTO Subcommittee on Maintenance Louisville, KY. 1. 1/4/2020. AASHTO Subcommittee on Maintenance Louisville, KY. 2. 1/4/2020. AASHTO Subcommittee on Maintenance Louisville, KY. 3. 1/4/2020. AASHTO Subcommittee on Maintenance Louisville, KY. 4. 1/4/2020.

karlaa
Download Presentation

1/4/2020

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. 1/4/2020 AASHTO Subcommittee on Maintenance Louisville, KY 1

  2. 1/4/2020 AASHTO Subcommittee on Maintenance Louisville, KY 2

  3. 1/4/2020 AASHTO Subcommittee on Maintenance Louisville, KY 3

  4. 1/4/2020 AASHTO Subcommittee on Maintenance Louisville, KY 4

  5. 1/4/2020 AASHTO Subcommittee on Maintenance Louisville, KY 5

  6. UDOT’s Pavement Marking Warranty Contract UDOT Maintenance Planning Division Rich Clarke, PE Engineer for Maintenance AASHTO Subcommittee on Maintenance Louisville, KY

  7. Background • 17 miles of I-15 reconstruction completed in time for the 2002 Olympics • 600 N to 10600 S • Design/Build contract with Pavement marking warranty attached • Contractor-Epoplex • Time-8 years (4 years initially with 4 year extension) • Material-Epoxy was a result of the contractor’s proposal to change from tape • Measures-Retroreflectivity & Presence AASHTO Subcommittee on Maintenance Louisville, KY

  8. 600 N. 10600 S. Salt Lake City Center Background (cont.) • Data collection subcontractor • 1st 4 years-Precision Scan • 2nd 4 years-BC Traffic • Expiration-summer 2010 • Evaluation • Epoplex did a good job • Easy to work with • Conscientious • Extra mile • Started looking at another contract in early spring 2010 • Suppliers approached us with interest in the contract I-15 AASHTO Subcommittee on Maintenance Louisville, KY

  9. Parameters • $5,000,000 budget • 5 year warranty • Established suppliers to act as prime contractor • Supplier chooses durable marking • Not solvent or waterborne • One application to last 5 years • Match existing marking geometry and contrasting • Remove all existing striping and messages • Recessing optional • Performance criteria • Striping • 200 mcd min. (white) • 125 mcd min. (yellow) • 90% presence/mile • Messages • 95% presence/message • Required to obligate mobile retroreflectometer data collection services • Data collection frequency • Just after installation • Annually in the spring for life of contract AASHTO Subcommittee on Maintenance Louisville, KY

  10. Parameters (cont.) • Additive bidding for the 3 prioritized segments • Price + Time bidding w/ incentives/disincentives • Lump sum payments yearly when all markings meet performance criteria AASHTO Subcommittee on Maintenance Louisville, KY

  11. Funding & Process • Initially planned on state maintenance funds • Put RFI out for comment & worked on RFP (Mar. 2011) • Federal IM money became available • Changed the process which added 2 months • Required 2 phases • RFQ-short listed qualified suppliers • Bid package AASHTO Subcommittee on Maintenance Louisville, KY

  12. Process Seg. 3 3rd Priority I-215 MP 26.75 to 28.35 Legacy Highway connection to Beck Street • Developed list of routes • High AADT • Too far away • Prioritized list • Developed quantities and estimate • Had to make product assumptions: • Couldn’t use solvent or waterborne • Used average of bid prices found for modified urethane, polyurea and epoxy • Initially had 20+ segments to choose from • Refined route list as we refined the estimate • Result was these segments: Seg. 1 1st Priority I-15 MP 292 to 309.65 114 S. north gore to 600 N. north gore Seg. 2 2nd Priority I-15 MP 285.93 to 291.79 Utah Co. line to 114th S. south gore AASHTO Subcommittee on Maintenance Louisville, KY

  13. Segment 1 • Highest priority • 114th S. north gore to 600 N. north gore • 17 miles-scope of previous warranty contract • Highest AADT (179,726) • 10 interchanges • 7 SPUIs • 3 freeway to freeway • 1 collector system • 2,144,986 ft. of striping • 255 messages Seg. 1 114th S. to 600 N. AASHTO Subcommittee on Maintenance Louisville, KY

  14. Segment 1 (cont.) • I-15/I-80/2100 S. freeway • Aka (Spaghetti Bowl) • Our messiest interchange • AADT spikes at 248,925 AASHTO Subcommittee on Maintenance Louisville, KY

  15. Segment 2 • 2nd highest priority • 114th S. gore to Salt Lake/Utah County line • 6.1 miles • 3 interchanges • 2 SPUI • 1 Diamond • 298,000 ft. of striping • 160 messages Seg. 2 114th S. to Salt Lake/Utah County line AASHTO Subcommittee on Maintenance Louisville, KY

  16. Seg. 3 I-215 Legacy Highway connection to Beck St. interchange Segment 3 • 3rd highest priority • I-215-Salt Lake /Davis county line to Beck Street interchange • 1.6 miles • 1 diamond interchange • 1 freeway/highway connection • 40,215 ft. of striping • 8 messages AASHTO Subcommittee on Maintenance Louisville, KY

  17. Status • Bid open in August • Too late to start work • Will start next spring • Good • Will allow better planning and scheduling • Will extend the 5 year warranty to 2017 • Condition of existing epoxy on I-15 is pretty good • Requires some minimal touch-up with waterborne to get through the winter • Interested to see what products and prices are bid: • We think: • Epoxy, or • Modified urethane ,or • Polyurea, or • A combination • Unique • Had previous warranty contracts via change order but this is the first time to solicit bids for only a pavement marking warranty scope • First time federal IM funds used for pavement markings AASHTO Subcommittee on Maintenance Louisville, KY

  18. Thanks! • Rich Clarke • richardclarke@utah.gov • 801-965-4120 • Ken Berg • kenberg@utah.gov • 801-965-4321 1/4/2020 AASHTO Subcommittee on Maintenance Louisville, KY 18

More Related