New York State Department of Transportation Kendrick Road Bridge Over I-390 Design-Build Project Request for Qualifications Informational Meeting June 27, 2012
Kendrick Road BridgeAgenda • Introductions and Opening Remarks • Project Overview • Questions and Answers
Kendrick Road BridgeRules of Contact Peter Russell Att: Kendrick Road Bridge New York State Dept. of Transportation Contract Management Unit, Non-Engineering and Design-Build Phone: 518-485-8620 Peter.Russell@dot.ny.gov
Kendrick Road Bridge Bike Path
Kendrick Road Bridge Goals: • Improve Area Traffic Patterns Widen Existing Bridge Provide Access Ramp to NB I-390 • Improve Bridge Service Life Improve Seismic Resistance Extend Deck Life • Deliver Project Safely, On Schedule, On Budget, and Environmentally Compliant
Kendrick Road Bridge General Scope of Work • Widening Kendrick Road Bridge Structure Widen Abutments, Pier, Pile Foundations, Embankments, Approach Slabs and Pavement Widen Bridge Deck, New Sidewalk, Lighting, Utilities, Railing Mill Top 2 Inches and Concrete Overlay Existing Deck • Provide Access Ramp to I-390 NB New Ramp, Pile Foundations, Piers and Superstructure Frame into Widened Steel Structure Replace Safety Shape and Noise Wall Acceleration Lane Pavement, Shoulder • Traffic Signal at Kendrick Rd./Ramp Intersection • Repair/Modify Canal Wall • Highway and Street Lighting • Provide WZTC
Kendrick Road Bridge General Scope of Work (cont.) • Other Work includes: • Bearing Replacement • Approach Guiderail Replacement • Possible Pedestal Repair/Modification • Possible Miscellaneous Steel Repair of Existing Structure • Steel Painting • Bike/Pedestrian Path Restoration and Improved Access • Coordination with Adjacent On-going Construction Project • Coordination with Canal Operations • Replace/Relocate Navigation Lights • Install/Replace/Relocate Traffic Signs and VMS Sign • Replace Existing Bridge Joints
Kendrick Road Bridge Schematic GENERAL DISCUSSION
Kendrick Road Bridge Procurement Schedule
Kendrick Road Bridge General Information • Lump Sum Design-Build Contract • Two Step Design-Build Procurement Process • Project Schedule • Total Duration 18 Months +/- • There will be a Payment Schedule provided in the RFP • Stipend Under Consideration by NYSDOT • Liquidated Damages may be imposed for missed milestones and final completion • All Environmental Permits and ROW by NYSDOT • Construction Related Permits by Design-Builder
Kendrick Road Bridge Quality Control (QC) • QC is Design-Builder’s Responsibility • Design-Builder shall appoint a QC Manager responsible for QC Plan for both Design and Construction • Design QC shall be by the Designer in accordance with the QC Plan • Construction Inspection shall be by an Independent Engineering Firm (Hired by the Design-Builder) • Materials Testing shall be by an Independent Testing Firm or Laboratory (Hired by the Design-Builder) • The Independent Testing Firm shall report to the Construction Inspection Firm who shall report directly to the Department • Offsite Plant Quality Control will be performed by the Department
Kendrick Road Bridge Quality Assurance (QA) • QA is Department’s Responsibility • The Department may perform QA on any of the Design-Builder’s activities • The Department may utilize an independent Consultant to perform QA of the Design-Builder’s Designs
Kendrick Road Bridge SOQ Evaluation and Selection • Pass/Fail Evaluation Factors • Legal • Financial • Proposal Responsiveness • Quality Evaluation Factors • Organization and Key Personnel (35%) • Experience of the Firms (28%) • Project Understanding (20%) • Past Performance (15%) • Backlog/Capacity (2%)
Kendrick Road Bridge Additional Information • Responses to Proposer Questions will be posted on the Department Website • Additional Reference Information to be Posted on Website: Design Report, Bridge Inspection Report, “As Builts”, Borings • Final Addendum will be issued by Monday, July 30, 2012 • There will be a Buy America Clause • There will be a DBE Participation Goal
Kendrick Road Bridge Project Website https://www.dot.ny.gov/main/business-center/DesignBuildProjects
Kendrick Road BridgeRules of Contact Peter Russell Att: Kendrick Road Bridge New York State Dept. of Transportation Contract Management Unit, Non-Engineering and Design-Build Phone: 518-485-8620 Peter.Russell@dot.ny.gov
Kendrick Road Bridge Questions??