An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. SP AusNetCapex – Approval Process

  2. AtoP Engineering Study Post Implementation Review AtoP Variation OARs Project Assessment Process Forecast Projects Unforecast Projects Need for Investment Project subject to economic/engineering analysis to justify proceeding, deferral or cancellation Efficiency of Solution Deferred and cancelled projects Significant variation in costs Delivery of Project Efficiency of Delivery

  3. Economic/Engineering Analysis Major report for large projects such as station rebuilds Working papers are combined in AtoP for more minor work Analysis may be for program of work rather than specific projects within the plan Contains the economic cost/benefit analysis of all technically feasible options Always considers the “do nothing” option. Both internally and externally generated reports are used

  4. Authority to Proceed (AtoP) Provides summary of economic/engineering analysis and a risk analysis (ie Implementation risks) Includes business case and sets internal budget May function as the economic/engineering analysis itself for minor projects Variation needed if AtoP budget is to be exceeded after the project is underway Variation must include explanation of cost increase and new economic/engineering analysis if required

  5. Order Approval Request (OAR) • Covers analysis of all tenderers and evaluation criteria. • Approval level is same as AtoP • Waiver of competition requires higher level of approval • Waiver of competition, where relevant, with explanation

  6. Post Implementation Review (PIR) Major projects subject to external PIR Explains cost over-runs, lessons learned and recommended improvements to processes Part of the feedback loop in the AM Process