150 likes | 161 Views
Explore the latest developments in the design and planning of the high-power RF test areas at CERN, focusing on objectives, layout, modulator procurement status, and pulse compressor advancements. Learn about milestones and deliverables.
E N D
High-Power RF Test Areas: Design & Planning Progress of the CERN Klystron Test Area CLIC WORKSHOP 2008 • Objectives • Layout • Modulator purchase status • SLED2 Pulse compressor • BOC Pulse compressor • Milestones and deliverables
Objectives Objectives: 1) Collaborate with CERN for the development and construction of a 12 GHz Klystron based Test Stand at CERN 2) Get an experience on critical components for a future additional test stand at CEA Saclay in the SYNERGIUM accelerator test area (352 MHz, 704 MHz and 1.3 GHz power sources already exist) CEA Participation to the CERN Test Stand: 1. High voltage modulator - Procurement, installation and tests with a 12 GHz klystron 2. RF Pulse Compressor - Design, fabrication and installation 3. RF Components - Procurements of loads or dir. couplers In the framework of exceptional contribution of France to CERN
HV Modulator: Call for tender 1) 1st Phase of Call for tender :Pre-selection of candidates • done in June 2008 • 3 companies pre-selected 2) 2nd phase of Call for tender : o Technical specification and commercial documents submitted to the 3 candidates o 45 days of delay for technical and commercial answer 3) Choice of the company 4) Adjudication of the contract We miss now the 12 GHz klystron characteristics to finalize the modulator technical specification (perveance, gun mechanical configuration, nb of power supplies…)
HV Modulator: Pre-selection criteria Preliminary specification: • Pulse repetition rate = 50 Hz but with an indication from the candidate if it is possible to provide a 100 Hz system • Peak voltage = 460 kV, Peak current = 310 A Pulse length = 1.5 µs (flat top), 2.3 µs (at FWHM). • Scope of the delivery: • High voltage pulsed power supply, auxiliary power supply (klystron focus magnet, filament, ion pump), high voltage oil tank, X-ray shielding, control-command system • Scope of the services: • Fabrication of the system, acceptance tests at factory, installation and acceptance tests on-site with a 12 GHz klystron from SLAC (delivered by CERN). Options: Option 1 – realization of a second modulator with the same specification (for CEA Saclay Test Stand) Option 2 – One additional year of maintenance Delay :12 months from the date of contract adjudication→ may become the critical path of the schedule Again, we need the 12 GHz klystron characteristics to be able to start the 2nd phase of modulator call for tender
Pulse compressor specifications Preliminary specifications Complementary specifications to be discussed and defined • Bandwidth • Time to reach the nominal vacuum level • RF pulse amplitude ripple • RF pulse phase ripple • Pulse to pulse stability (amplitude) • Pulse to pulse stability (phase) • Thermal stability • Cooling circuit • RF leakage • X-ray radiation • Ability to vary the pulse amplitude • Ability to vary the pulse length • Ability to vary the slope In order to study different philosophies of conditioning
SLED2: Pulse waveform after compression • Propagation of the TE01 mode Input PC power amplitude (MW) Input PC power phase (deg) L : Length of the delay line Td :Time delay = 2L/vg = length of output compressed pulse C : Light velocity ω = 2πF with F operating frequency p’01 : 1st root of J’0 the derivative of J0 the bessel function of kind p’01 = 3.832 a : circular waveguide diameter Time (ns) Output PC power amplitude (MW) Length of delay line (m) 140 MW, 300 ns Circular waveguide diameter L=42m, a = 90 mm Time (ns) Compressed pulse length (ns)
SLED2: Vacuum short study Cu OFHC Pre-heating at 950°C under vacuum during 10h bake out at 120°C q =1.8 x 10-9 Torr.L.s-1.m-1 Delay line pressure (Torr) Design Level: 4E-9 Torr Need at least 6 RF pumping ports, 3 ports on each delay line Sensitivity to the waveguide diameter? Hybrid coupler + mode converter Delay line length (m) Pumping port Variable short circuit Ion pump 30 L/s F. Peauger
SLED2 at SLAC SLED-II concept was already demonstrated with NLCTA operation and runs routinely for high gradient research S. Tantawi et al. Results: With a single 50 MW klystron (1998) With four 50 MW klystron and multimode PC (2005) Recommendations from SLAC for our system are welcome (vacuum, tolerances for fabrication, mechanical support and alignment…) BUT: installation in CTF3 buildings may be problematic and cost could be high → Alternative solution: X-band Barrel Open Cavity (BOC)
BOC: Preliminary RF design With a TM20,1,1 mode: a = 103.75 mm L2 = 100 mm R1 = 10 mm F0 = 11.9968 GHz Q0 = 169465 with copper L1 = 40 mm ratio = 0.848 ΔF/Δa = -0.1182 GHz/mm L1 With = skin depth R1 Inner radius a L2 Elliptic profile (ratio) • Other modes will be studied: Q0 = 200000 with a=130 mm, … • Simplification of the cavity profil - Optimisation of H and ө for a given inner radius a… ө H
BOC: Pulse waveform after compression Input PC power phase (deg) Input PC power amplitude (MW) • Q0 = 160000 • β=Qx/Q0 = 8 • Reflexion coef = 0.777 • Filling time = 0.471 µs Phase step of 1.3 rad and linear variation from 1.3 to π rad Time (ns) Output PC power amplitude (MW) 120 MW, 250 ns Slope phase step: 20ns not within spec (150MW - 300ns) but interesting first results is worth being more studied and optimized Time (ns) Flat top BOC: 255 ns Filling BOC: 1.3 µs
BOC: Coupling • Quarter wavelength multi-hole coupler: TM20,1,1→ 20 x 4 = 80 holes (m=20) • Synchronism conditions between surrounding waveguide and cavity: With wavelength = 24.995 mm R tx w Δ Tz/2 a
Milestones and deliverables 1. High voltage modulator • Participation in the klystron design review at SLAC Oct. 2008 • Tender for modulator purchase Nov. 2008 • Choice of the supplier in collaboration with CERN Jan. 2009 • Modulator production follow-up Feb 2009 to Feb 2010 • Delivery of the modulator to CERN, installation and high power tests with a SLAC klystron Feb. 2010 2. Pulse compressor • Preliminary Design Review : decision between SLED2 and BOC July 2009 • Delivery of the Pulse Compressor to CERN, installation and high power tests with a SLAC klystron Feb 2010 3. RF Components • Participation in 12 GHz component review at CERN Oct. 2008 • Participation in component testing at SLAC Nov. 2009 • High-power testing at CERN Feb. to June 2010
Conclusion Interesting and challenging program with significant R&D effort We are waiting for the klystron characteristics in order to finalize the modulator technical specifications and continue the call for tender which is planed in Nov. 08 for the end phase Design studies have started for Pulse Compressor, with SLED2 as baseline and BOC as option → decision in July 2009 Preliminary Design Study started with Thales ED (S. Sierra) for the study and realization of an additional test stand at CEA Saclay (except the klystron): delivery in Nov. 08 Acknowledgments for preliminary discussions and work: G. Mcmonagle, K.M. Schirm, I. Syratchev Thank you for your attention