1.12k likes | 1.35k Views
Steel Valley School District. District Feasibility Study Community Dialog June 22, 2004. Agenda. Introduction Secondary school discussion Presentation on secondary school issues Table discussion on secondary school issues Summary of table discussions Elementary School Discussion
E N D
Steel Valley School District District Feasibility Study Community Dialog June 22, 2004
Agenda • Introduction • Secondary school discussion • Presentation on secondary school issues • Table discussion on secondary school issues • Summary of table discussions • Elementary School Discussion • Presentation on Elementary school issues • Table discussion on Elementary school issues • Summary of table discussions • Closing
Study Parameters and Direction • Evaluate the followings items at the High School / Middle school • Indoor athletic facilities • Auditorium • Lower level of middle school • Evaluate Elementary Facilities • Make Recommendations
Tasks Completed to Date • Evaluated facilities (June 9 and June 12, 2003) • Questionnaires and discussion with district faculty and staff (June 13, 2003) • Board workshop (September 11, 2003) • Developed options • Draft of study delivered to district (November 7, 2003) • Board Workshop (February 23,2004)
Enrollment Evaluation (PDE projections 2002 enrollments) Year K 1-5 6-8 9-12 total 2003 - 2204 112 827 564 716 2219 2004 – 2005 115 774 537 742 2168 2005 – 2006 127 742 530 728 2127 2006 – 2007 128 713 518 737 2096 2007 – 2008 125 700 497 717 2039 2008 – 2009 123 689 490 675 1977 2009 – 2010 120 702 441 680 1943 2010 – 2011 118 709 411 651 1889 2011 – 2012 115 689 401 629 1843 2012 – 2013 113 683 421 590 1807 Note: These projections do not include the effects of the Propel charter school
Steel Valley High School Main Issues • Gymnasium • Provide additional gymnasium space • Renovate existing gymnasium and locker rooms • Provide storage and concession stand • Auditorium • Replace seating, lighting system, stage curtain • Middle school • Provide additional classrooms in lower level
Steel Valley High School Gymnasium Option 1 • Construct new gymnasium
Steel Valley High School Gymnasium Option 2 • Renovate existing pool into gymnasium
Steel Valley High School Renovate existing Gym and Locker rooms • Replace and level floor • Replace Bleachers • Rearrange lockers for proper supervision • Repair cracks • Improve ventilation • Provide second exit from gym
Steel Valley High School • Provide storage and concession stand
Steel Valley High School Auditorium Replace seating, Lighting system, Stage curtain, Rigging
Steel Valley High School Middle school • Provide additional classrooms in lower level
Steel Valley High School • Secondary School Table Discussion • Gymnasium • Provide additional gymnasium space • Renovate existing gymnasium and locker rooms • Provide storage and concession stand • Auditorium • Replace seating, lighting system, stage curtain • Middle school • Provide additional classrooms in lower level
Options • Minimal renovations to all 3 schools based on priorities on building evaluation forms. • Renovations required to receive reimbursement from PDE • Renovations and additions to Woodlawn for district wide K-5, Convert Franklin into Administrative center • Demolish Woodlawn, construct new district wide K-5 school, Convert Franklin into Administrative center. • Renovate Woodlawn to replace Park, replace Barrett for K-5, Convert Franklin int administrative center.
Options Option 1 Priority levels • Level 1 - items that must be done in order to meet current building codes • Level 2 - items that are recommended to do to enhance the learning environment • Level 3 – items that need to be completed and will be less expensive to do as a part of a larger construction project
Franklin Elementary SchoolOption 1 Priority 1 • Repair cracks, reinforce foundation walls and ventilate crawl space • Repoint masonry • Replace doors • Provide ADA Signage • Correct ADA deficiencies for toilet partitions and toilet accessories • Repair steam leaks • Repair lining of chimney • Install backflow preventer • Abandon and repair emergency battery packs or replace generator
Franklin Elementary SchoolOption 1 Priority 2 • Repair or replace flagpole • Replace exterior doors and frames • Adequate casework in classrooms and storage • EWC’s to be provided at an appropriate height • Install second boiler • Investigate ventilation dampers/perform steam trap maintenance • Repair fixture leaks • Replace lighting
Franklin Elementary SchoolOption 1 Priority 2 • Provide exterior lighting • Replace toilets and urinals • Provide appropriate site lighting • Provide permanent housing for district admin to remove trailers • Provide Location inside of classrooms for student badges • Provide extended day Kindergarten and library • Separate district admin and classrooms
Franklin Elementary SchoolOption 1 Priority 3 • Replace windows • Replace vinyl tile • Convert to a hydronic system • Install DDC controls • Replace piping system and fixtures • Install sprinkler system • Provide new electrical service entrance • Update copper electrical distribution • Replace phone system • Replace PA system • Provide lightning protection • Replace security system • Move office to current library location to monitor entry
Franklin Elementary SchoolOption 2 Renovate building to receive Reimbursement • Move school functions out of administrative wing • Additions to enable removal of trailers • Provide library
Franklin Elementary School Kindergarten Wing CR CR Library Block Access From Admin to Elementary School Admin School Entry District Admin Wing District Admin Entry Addition
Franklin Elementary School • Option 3 ,4, and 5 Convert to Administrative Center Community Use M.P. Room/ Faculty Training Possible rental space – daycare – office etc. Office of the Superintendent Remove existing trailers Business Office