1 / 20

Mini-Grid Based on Renewable Energy (Biomass) Sources to Augment Rural Electrification

Mini-Grid Based on Renewable Energy (Biomass) Sources to Augment Rural Electrification. Implemented by UNIDO. Project objective. To promote renewable energy (biomass) based on mini-grid as an alternative to diesel based energy generation systems in Nigeria. Project outcomes.

keaton
Download Presentation

Mini-Grid Based on Renewable Energy (Biomass) Sources to Augment Rural Electrification

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Mini-Grid Based on Renewable Energy (Biomass) Sources to Augment Rural Electrification Implemented by UNIDO

  2. Project objective To promote renewable energy (biomass) based on mini-grid as an alternative to diesel based energy generation systems in Nigeria

  3. Project outcomes • Preparatory works completed for facilitating replication in the identified potential sites • Acceptance by stakeholders on the technical and financial viability of selected site for setting up the biomass based mini-grid for rural electrification • Conducive financing and policy environment for promoting investments in rural mini-grids in place • Capacity of local planners, institutions and experts for RE based mini-grid enhanced

  4. Outcome 1: Preparatory works completed forfacilitating replicationin the identified potential sites • Project inception workshop organized • Project Steering Committee (PSC) inaugurated • Project Management Unit (PMU) established • National Project Manager recruited • Detailed Engineering studies, TOR for EPC contract prepared

  5. Outcome 2: Acceptance by stakeholders on the technical and financialviability of selected site for setting up the biomass based mini-grid for rural electrification • Full-scale feasibility study with business plan conducted • Investment forum organized • Project stakeholders/financiers identified and organized with established Board • Project stakeholders agreement developed and endorsed by project owners • Project stakeholders exposed to biomass technology through trainings and study tours • Project bid documents prepared and launched • Bidders have been selected and evaluated • Preferred bidder selected for the Engineering, Procurement and Construction (EPC) • EPC Contract signed • Project equity finance determined and agreed by project owners • Project debt finance being processed under the Power and Aviation Intervention Fund (PAIF)

  6. Outcome 3: Conducive financing and policy environment for promoting investments in rural mini-grids in place • Consultation and arrangements ongoing with Energy Commission of Nigeria (ECN) and the National Electricity Regulatory Commission (NERC) for the review of policies and documents

  7. Outcome 4: Capacity of local planners, institutionsand experts for RE based mini-grid enhanced • Training of staff of project owners on Renewable Energy Technologies (RETs) conducted • Capacity building for key project stakeholders planned and awaiting approval by Federal Ministry of Finance for implementation

  8. Project budget • GEF: 2,681,800USD • Co-financing: 11,935,00USD

  9. Enabling Activities to Review and Update the National Implementation Plan for the Stockholm Convention on Persistent Organic Pollutants (POPs) Implemented by UNIDO

  10. Project objectives • Update and review the National Implementation Plan (NIP), have it endorsed and submitted to the Stockholm Convention Conference of Parties (COP); and • Enable participating stakeholders to manage the additional POPs with newly developed technical skills, expertise and awareness

  11. Project components • Coordination mechanism and awareness raising • Inventories of new POPs and NIP review • National capacities assessment and priority setting for management of new POPs • NIP formulation, endorsement and submission • Monitoring and evaluation

  12. Project partners and budget • Federal Ministry of Environment • Federal Ministry of Finance (FMF)  • Federal Ministry of Health (FMoH)  • Federal Ministry of Agriculture and Rural Development (FMA&RD)   • Nigeria Customs Service (NCS)   • National Planning Commission (NPC)  • PHCN now Transmission Company of Nigeria (TCN)  • Basel Convention Regional Coordinating Centre (BCRCC)  • The Academia  • Project budget: $225,016

  13. Project progress • Steering committee to be inaugurated in April 2014 • NIP inventory training to take place in May 2014

  14. Scaling up Small Hydro Power (SHP) in Nigeria Implemented by UNIDO

  15. The project • Project objective Promote investment in Renewable Energy Technologies (RETs) • Expected focal area outcome: Investments in RETs increased • Expected focal area output: 5.9MW RE capacity Installed • Project Implementation Cost: 23,267,917.72USD

  16. Project components • Human and institutional capacity building • Upgrading the capacity for local fabrication of SHP turbines and control systems in Nigeria • Promoting investment in SHP sector • M&E and knowledge management

  17. Lessons of experience Completed sites • WAYA Dam, BauchiState Capacity: 2x75kW • Ezioha – Mgbowo, Enugu State Capacity: 35 kW • KakaraTea Factory, Taraba State Capacity: 2x200kW • Local fabrication of SHP turbines and control systems

  18. Lessons of experience (cont’d) Ongoing sites • Amoke, Benue State Capacity: 3x40 kW • Ikeji-Ile, OsunState Capacity: 2x35kW • OOPL Complex,OgunState Capacity: 15 kW and 2 kW

  19. Progress made • CEO endorsement document ready • Working on the co-financing letters from partners

  20. Project partners • Federal Ministry of Environment • Federal Ministry of Power • Federal Ministry of Water Resources • Energy Commission of Nigeria • Bank of Industry • State Governments • Private Investor

More Related