1 / 21

CDR Mark Geronime, CEC, USN Assistant Operations Officer Central IPT June 28, 2007

Naval Facilities Engineering Command Southwest. Central IPT – USMC. CDR Mark Geronime, CEC, USN Assistant Operations Officer Central IPT June 28, 2007. 1. Briefing Topics. NAVFAC SW Mission Central IPT Overview USMC Bachelor Quarters Program Grow the Force (GTF)

Download Presentation

CDR Mark Geronime, CEC, USN Assistant Operations Officer Central IPT June 28, 2007

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Naval Facilities Engineering Command Southwest Central IPT – USMC CDR Mark Geronime, CEC, USN Assistant Operations Officer Central IPT June 28, 2007 1

  2. Briefing Topics • NAVFAC SW Mission • Central IPT Overview • USMC Bachelor Quarters Program • Grow the Force (GTF) • Business Line Team Execution • Base Development • Real Estate • Environmental • Capital Improvements

  3. The NAVFAC Mission • Provide facilities acquisition, installation engineering/support and Seabee/contingency engineering services to the Navy, Marine Corps and other Department of Defense and federal agencies

  4. NAVFAC SW BUSINESS VOLUME – FY07 Volume by Business Line NAVFAC SW Total FY07: $1.6 Billion Volume by Client

  5. Central IPT

  6. Marine Corps InstallationsWest Within NAVFAC SW AOR: • 58% of Land Assets (acres) • 48% of Buildings (ft2) • 38% of Plant Repl Value ($)

  7. USMC BEQ Initiative • Overall Program • Initiative: 50 Bachelors Quarters FY08-FY13 • Eliminates 20,000 bed deficiency • Total Program $1.3-1.7B • West Coast Slice (Includes BQs previously programmed) • 25 BQs at Camp Pendleton • 4 BQs at 29 Palms • 1 BQ at Yuma • 1 BQ at Barstow • Best-of-Breed Standards • CMU, Standing Seam Roof, Standard room configuration, … • Recent BEQs at 29 Palms served as the benchmark • 80% of RFP will be common East/West Coast

  8. BEQ Initiative (2008-2009) MCRD San Diego

  9. BEQ Initiative • Acquisition Strategy: East Coast & West Coast Contracts with Options and Escalation through FY09; • Pros: • Will attract large contractors • Optimize economy of scale • May significantly increase speed of delivery • Creates opportunity for less risk in pricing • Cons: • Potential bonding capacity issue for other than the largest contractors • Reduces/Eliminates Small Business prime contractor opportunity

  10. Grow the Force • Initiative started in early 2007 • USMC Growth for MCI West • MCB Camp Pendleton – 3,000 PN • MCAS Camp Pendleton – 900 PN • MCAS Miramar – 400 PN • MCAS Yuma – 100 PN • MCAGCC 29 Palms – 2,000 PN

  11. NAVFAC SW MILCON Program AS OF FEB 2007... $M NAVFAC Southwest Historical Execution NAVFAC Southwest Budgeted Projections Base Closure and Realignment Workload $276M $ 590M $ 623M $ 430M $ 428M $250M $333M $ 463M $ 453M $ 430M

  12. NAVFAC SW MILCON Program AS OF JUN 2007... $M Historical Execution USN MILCON USMC MILCON $276M $ 936M $1.2B $ 1.2B $ 428M $250M $333M $ 1.4B $ 453M $ 430M

  13. Grow the Force • Base Development: • Prepared Interim Laydown Facility DD 1391s • MILCON DD-1391 Preparation: Due to HQMC this fall • Utilize planning contracts to provide mini master plans • Real Estate: • Land acquisition at several locations to support growth • Environmental: • NEPA work for temporary and permanent construction • Capital Improvements: • Validated FY07 Temporary Facility MILCONs • Validated FY08 MILCONs • Cost Certified FY09 MILCON Program • Leveraged other IPTs for FY08 Accelerated MILCON RFP Development and Design Management • Developing acquisition strategies for project execution and design management

  14. Business Line Execution

  15. Base Development (Planning) • What We Do • Comprehensive planning services: • Establish Plan of action & milestones (POAM) • Develop Requirements - BFRs • Analyze existing assets (Building walk-through, use, identify surpluses/deficiencies) • Establish a Capital Improvements Plan (CIP) to satisfy deficiencies • Prepare DD1391s, Cost Estimates, Economic Analysis • Prepare Master Plan to provide for the logical & orderly execution of the CIP • Provide a wide variety of misc. studies (Traffic/Site Studies, AICUZ/RAICUZ) • Recent Partnerships with Marine Corps • Visioning Session, MCB CPEN • Project Documentation (DD1391s) for all phases of CA MOUT, 29 Palms • POM 10 Project (DD1391s) Documentation, Barstow & 29 Palms • Integrated Functional Plan, Combined Arms (CA) MOUT, 29 Palms • MWTC Bridgeport Master Plan • Range Complex Master Plan, 29 Palms • Over 20 active planning contracts at MCI West bases

  16. Real Estate • What We Do • Acquisition • Management • Disposal • Appraisal • Survey/Mapping • Recent Partnerships with Marine Corps • Public Private Venture • Agricultural Out Leases • State of CA/San Onofre State Beach Lease • Cell Communications Service at Camp Pendleton

  17. Environmental • What We Do • Compliance • ER,N, MRP • NEPA • Natural and Cultural Resources • Recent Partnerships with Marine Corps • MCI West Environmental • Conservation EXPO participation • ER,N funds Plus Up ($190M for MCI West bases) • 20 active EA/EIS for USMC MILCON or operations

  18. Capital Improvements • What We Do • Execution – MILCON & M2R2 • Project & RFP Development • DD 1391 Validation • ROICC Technical Support • Recent Partnerships with Marine Corps • FY07 MILCON Execution ($246M) --- 50% awarded through May • FY07 M2R2, GWOT and Env Projects (~$65M) --- 40% awarded through May • FY08 MILCON RFP Development ($650M program) • MARSOC Program: ~$100M over FY07 & 08 • DBOM Program • M2R2 & ES Programs • P-110/110A DB Project • BEST OF BREED • BEQ Program: Over $1B from FY07-12 • Furnishings, Fixtures & Equipment (FF&E) Process Improvement

  19. FY 07 / 08 Regional MAC Contracts • NoCal Non-Industrial MACC • $500M over 5 Years – ( $7M - $30M Task Orders ) • SoCal Non-Industrial MACC • $500M over 5 Years – ( $7M - $30M Task Orders ) • NoCal 8(a) General Construction MACC • $100M over 5 Years – ( $500,000 - $3.5M Task Orders ) • SoCal 8(a) General Construction MACC • $100M over 5 Years – ( $500,000 - $3.5M Task Orders ) • Waterfront MACC • $100M over 5 Years – ( $500,000 - $10M Task Orders ) • Fire Protection MACC • $100M over 5 Years – ( $500,000 - $3.5M Task Orders ) • Airfield and Heavy Duty Paving MACC • $100M over 5 Years – ( $500,000 - $15M Task Orders ) 2

  20. Summary • Committed to providing optimum support to the Marine Corps mission at lowest cost to the taxpayer • Committed to our partnerships with SBA and AGC • Committed to meeting/exceeding Small Business Contracting goals • We appreciate everything the members and sustaining firms do for our industry

  21. SAME Orange County Post --Thank you for the opportunity!