Sequence of Events Recording for Kardia Power Station Greece

Sequence of Events Recording for Kardia Power Station Greece. Ian Loudon Omniflex International Marketing and Sales. Omniflex. Omniflex South African Manufacturer of Industrial Electronic Products Founded 1965 as Conlog became Omniflex 1996 50% of Turnover exported

keilah
Download Presentation

Sequence of Events Recording for Kardia Power Station Greece

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Sequence of Events Recording for Kardia Power Station Greece Ian Loudon Omniflex International Marketing and Sales

  2. Omniflex • Omniflex South African Manufacturer of Industrial Electronic Products • Founded 1965 as Conlog became Omniflex 1996 • 50% of Turnover exported • Sales Office JHB, UK, Australia Head Office Durban • Wonderware and Sequence of Events recording since 1988 ESKOM, Sasol, Natref

  3. Introduction This Project improves an ageing Coal Fired Power Station Root Cause Analysis by 90% Kardia Power Station Greece

  4. Introduction Project Solution Agenda Benefits Considerations Summary

  5. Kardia Power Station Greece Up to 50% of Greece’s Electricity from Coal (Lignite) 6 Lignite Fired Stations Agios DimitriosAmyntaioFlorinaKardiaMegalopolisPtolemais How much coal is required to run a 100-watt light bulb 24 hours a day for a year?

  6. Background to the Project Location : GreeceOperator : Public Power CorpConfiguration : 4 X 300 MWOperation : Since 1975 ……Fuel : LigniteBoiler : Stein, Ganz-RockT/G supplier : Alstom, LMZ, TeploenergoEPC: Zarubezhenergoproekt T/G Turbine Generator EPC Engineering Procurement Construction

  7. Business Objective • Plant Optimization • Reduce Downtime • Effective Alarm Localization • Nuisance Alarm Identification • High Availability • Cost effective Solution

  8. Operational Objectives • Root Cause Analysis • Alarm History • Local Alarm Indication • Fast and Reliable Event Capture • Redundancy of I/O Processors

  9. Introduction Project Solution Agenda Benefits Considerations Summary

  10. Selection of Solution • Local SI for Local Support • Wonderware SCADA selected for • Ease of configuration • Minimal effort to integrate Date and Time Stamp at source event streams through OPC server

  11. Sequence of Events Recording System

  12. System Implementation • 960 Relay Contact Inputs COS monitoring • 960 Alarm Statuses Annunciated • Input discrimination to 200μseconds • Minimum Pulse Width 500μseconds • Time Stamping Accuracy 200μseconds

  13. System Diagnostics

  14. Historical Alarms

  15. Alarm Summary

  16. Time Synchronization • GPS Station Time • OPC server Service

  17. Controller Redundancy • Dual Controller • Includes Queue Services

  18. Topology SCADA Primary OPC Marshalling Panel Conet Field Inputs Ethernet Secondary Modbus CAN

  19. Disadvantages of Poll Response Disadvantages of a poll/response network · Poll/Response uses %100 of available bandwidth. · The data "Transport" is the "Application". You can't break them apart. · One protocol for all field equipment limits deployment of new technology & impedes migration to new topologies. · It is not a "managed" network. · One-to-One data relationship between the Host and field equipment Master Slave

  20. Producer Consumer Subscription Consumer Application 1 Middleware Message Broker Eg Queue Service Producer eg SOE System Consumer Application 2 Publish Subscribe Subscribe Consumer Application 3 • Advantages: • Network Traffic Minimized • Efficient use of Network Bandwidth • Multiple consumers

  21. System Implementation • In House Engineering and Testing and Configuration, SCADA, OPC, Maxiflex 1 week • Local Panel Alarm Annunciators via Modbus RS485 • Wonderware SCADA Final Configuration On Site • Copy Paste for Second System 2 Days In House Engineering and Testing

  22. Introduction Project Solution Agenda Benefits Considerations Summary

  23. Benefits / Goals Achieved • Plant Optimization  • Reduce Downtime  • Effective Alarm Localization  • Nuisance Alarm Identification  • High Availability 

  24. Benefits / Goals Achieved • Root Cause Analysis  • Alarm History  • Local Alarm Indication  • Fast and Reliable Event Capture  • Redundancy of I/O Processors 

  25. Realised Benefits • 90% improvement in Root cause analysis • 25% improvement in Generating Availability • 40 to 50% time saving in Maintenance • Huge Saving on Hard Wired Annunciation • Project Implementation Short • End User Empowerment on system usage, migration and on going improvement • Rapid Deployment of next Generator system

  26. Introduction Project Solution Agenda Benefits Considerations Summary

  27. Lessons Learned • Learn to Speak Greek ! Real Greek • Partnering with local Wonderware SI’s essential • Preconfigured Wonderware for Front end Hardware from Factory simplifies field work

  28. Introduction Project Solution Agenda Benefits Considerations Summary

  29. Conclusions • Wonderware was a good choice for seamless integration of Date and Time stamped events into an HMI for management of Alarm and Events. • Wonderware Presence worldwide presented this opportunity for us from a South African and UK Base.

  30. Project summary • “The system works well and enables incidents to be tracked very efficiently”.Ilias Kalaitzis ,Project Engineer, Control Systems

  31. Project Summary • Project Delivered in 2008 on time during Shut Down of Generator Unit Period 16 Weeks Entirety • Second Unit simple Copy and Paste for SOE Configuration. Completed Dec 2008 • We are expecting orders for the balance of 2 Generator Sets