1 / 14

Midland Power Utility Corporation

Midland Power Utility Corporation. Distribution System. Midland PUC Customers. 6124 Residential 747 Commercial 29 Large Industrial 4 44KV Feeders 6 Sub Stations 3 8 KV Feeders 23 4 KV Feeders. Load Profile. 29 Large Industrial Cust.

keira
Download Presentation

Midland Power Utility Corporation

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Midland Power Utility Corporation Distribution System Midland Power Utility Corporation AGM for 2012

  2. Midland PUC Customers • 6124 Residential • 747 Commercial • 29 Large Industrial • 4 44KV Feeders • 6 Sub Stations • 3 8 KV Feeders • 23 4 KV Feeders

  3. Load Profile 29 Large Industrial Cust. 6871Residential & Commercial Cust.

  4. 4 - 44 KV Feeders

  5. Midland PUC 6 Substations

  6. 3 - 8 KV Feeders

  7. 23 - 4 KV Feeders

  8. Sub Station Study • Rondar completed the Study in 2006 • Recommendation to upgrade each Station • Brandon, Fourth, & Dorion – Full upgrade • Scott, Montreal, & Queen – Partial upgrade Montreal Substation

  9. Substation Upgrade Old Dorion Substation

  10. Substation Upgrade New Dorion Substation

  11. Safety, Capacity, & Flexibility • Improved safety features • Greater Capacity • Increased Flexibility • Long Term Load Forecasting • Substations – Integral for sustainability Queen Substation

  12. Capital Projects 2012 • Montreal Substation upgrade • William Street pole line rebuild • Pratt’s Field pole line rebuild • Pad Mount transformer upgrade • Pole Mount transformer upgrade • Selected pole replacements • Kabar replacements

  13. LED Street light upgrade • 3 Year Project • 1540 street lights • 2013 Goal to change 500 fixtures focusing on the least efficient. • 2014 Change 500 plus remaining from 2013 • 2015 Complete remaining fixtures

  14. Thank-you