California Roundup: Summary of DR Activity in California. John Goodin Lead, Demand Response 2008 National Town Meeting on Demand Response June 3, 2008. California Energy Action Plan.
E N D
California Roundup:Summary of DR Activity in California John Goodin Lead, Demand Response 2008 National Town Meeting on Demand Response June 3, 2008
California Energy Action Plan • The “loading order” identifies energy efficiency and demand response as the State’s preferred means of meeting growing energy needs. • The 2008 Energy Action Plan update lists several key DR related action items: • Adopt load-management standards to achieve a demand response infrastructure. • Utilize advanced metering, tariffs and automated DR infrastructure in the development of DR programs. • More progress on dynamic pricing rate design reform for all customer types. • Develop DR load impact and cost-effectiveness protocols. • Modify retail programs to more fully participate in the CAISO’s wholesale market structure.
Retail Activity • CEC Load Management Standards Proceeding • CPUC Demand Response Proceeding • Utility 2009-2011 DR Program Applications • Development of Dynamic Tariffs • Large Scale Deployment of AMI
Regulatory Proceedings in California- CEC • CEC Load Management Proceeding (08-DR-01) • Explore and consider any rate tariffs, equipment, software, automatic technologies, and other measures and regulations that would be appropriate to achieve a price-responsive electricity market • Explore the coordination of regulatory authority of demand response efforts across investor owned and publicly owned utilities in the state
Regulatory Proceedings in California- CPUC • CPUC Demand Response Rulemaking (R.07-01-041) • Load Impact Protocols • Long-term planning and Resource Adequacy purposes • Day-to-day operational and procurement needs (CAISO and utility) • Cost-effectiveness Protocols • Goals • Proposed decision due out shortly • Integration with CAISO Market Design • Utility DR program applications for 2009-2011 • Filed yesterday (June 2nd)
Wholesale Activity • Driving the need for Market Integration • Demand Response Working Groups • Enhanced Functionality in New Market Design
Integrating Intermittent Renewable Resources Total Wind Generation Installed Capacity = 2,648 MW Wind Generation at Peak CAISO Wind Generation July 2006 Heat Wave 1,200 1,000 800 MW 600 400 200 0 07/19/06 07/20/06 07/20/06 07/21/06 07/21/06 07/22/06 07/22/06 07/23/06 07/23/06 07/24/06 07/17/06 07/17/06 07/18/06 07/18/06 07/19/06 07/24/06 07/16/06 07/25/06 07/25/06 07/26/06 07/26/06 Wind Generation Wind Generation at Peak
Retail – Wholesale Integration in California Five (5) Working Groups and the Lead Agency: • Vision for Demand Resources- CPUC • DR Participation in MRTU Release 1 - CAISO • DR Participation in MRTU Post Release 1- CAISO • Demand Resource Product Specification- CEC • Infrastructure for Demand Resources- CEC
Proposed CAISO Market Design Enhancements Model DR with the Flexibility of a Generator
Questions? Contact Info: John Goodin (916) 608-7154 jgoodin@caiso.com