An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. LAV construction & installation status Matthew Moulson for the LAV Working Group NA62 Photon-Veto Working Group Meeting CERN, 01 April 2014

  2. LAV installation: Activity at CERN • A1-A8 status: • HV & signal cable supports for A6-A7-A8 installed • Measurements taken for HV & signal cable supports for A9-A10-A11 • HV recabled A1-A3, with reflected cables • HV cabled for A4-A8 • Signal cables for A1-A11 with correct impedance ready • A1-A8 fully tested, about 10 bad channels • Almost certainly loose pins on connectors on vacuum side of flanges • A1-A8 installation work: 7-18 April • 2 physicists + 2 technicians • Installation of FEE boards & signal cabling • Repair and test of problematic channels • A10-A11 installation: • 15-24 May, if missing sections of blue tube finished on time • Delays due to availablity of Stycast resin for interior coating

  3. Cable supports for A6-A7-A8

  4. A12 construction status: Fantini • Welds between sectors complete: rings ready for milling machine • Some problems with milling machine → small delays • Predicted delivery still 15 April – in time for A12 completion by 1 Aug

  5. A12 construction status: Frascati

  6. A12 construction status: Frascati 263 blocks reinforced – 121 processed in oven before rewrapping

  7. Refinements to wrapping technique Attempt to speed up and simplfy wrapping procedure and minimize use of PVC tape Use of cleaning stand to check for light leaks