Group Commitments. & Resources for Physics. Reminder – Today’s situation. Tilecal ( Carles, Ilya, Matteo C., Matteo V., Ulla ) Calibration electronics commisioning General Tilecal commissioning Trigger EF Infrastructure ( Hegoi, Martine, Serge )
E N D
Group Commitments & Resources for Physics Martine Bosman - Group Commitments - IFAE Atlas Dec.21 2005
Reminder – Today’s situation Tilecal (Carles, Ilya, Matteo C., Matteo V., Ulla) Calibration electronics commisioning General Tilecal commissioning Trigger EF Infrastructure (Hegoi, Martine, Serge) PESA (Carlos, Ester, Martine, Pilar) Physics – Combined Performance gamma+jet & Jet reconstruction/calibration/algorithms (Carolina, Martine, Sigrid) “Trigger aware” analysis (Carlos, Pilar) Martine Bosman - Group Commitments - IFAE Atlas Dec.21 2005
Group Commitments - Tilecal Calibration electronics commisioning + development commissioning of all integrators – ADCi – ROBs Beginning 2006 FT at CERN – then on call “shaft-board” (control of 3 calibration systems) ½ 2006 design / prototype cycle Carles + Ilya production & commissioning Carles + Ilya++ Calibration data readout & treatment (via DCS) Ulla General Tilecal commissioning MobiDaq based: for commissiong and standalone cosmic (Ulla) Integrator expert (Ilya++=team) Cosmic Runs: 2006-2007 (some involvment) Tilecal Standalone Cosmic Run (2006), Combined wih Muon System (from Feb2006) & LAr (from May2006) Long-term M&O commitment to Tilecal: 0.5FT + 0.5Student Martine Bosman - Group Commitments - IFAE Atlas Dec.21 2005
Group Commitments - Tilecal Availability: Ulla Tilecal ( 90%) until fall 2006, 10% after ready for strong physics involvment Ilya Tilecal ( 70%) until fall 2006, 30% after 50% Physics after fall 2006 MatteoV Tilecal( 50%),Tesina Tilecal(50%) until fall 2006 50% after starting PhD Physics >> around fall 2006 new “pool” of people available for physics Martine Bosman - Group Commitments - IFAE Atlas Dec.21 2005
Group Commitments – Trigger – Event Filter Finalize design and implement all functionalities Trigger, calibration, monitoring 2006 (Serge 80%, Martine 10%, + ??) Testing functionality, performances, scalability & robustness in testbeds & Cosmics run 2006 (Hegoi 100%, Serge 20%, +??) Commissioning of the EF system in Atlas First ½ 2007 M&O of the Event Filter Second ½ 2007 onwards 0.5 FTE + 0,5 Student >> starting 2007 Serge available 50% for physics Martine Bosman - Group Commitments - IFAE Atlas Dec.21 2005
Group Commitments – Trigger – PESA Finalize design and implemention of system July 06: algorithm review completed do slice tests with DC3/CSC data Dec 06: blind test of HLT selection (Carlos 50%, Ester 50%, Pilar) Integration with detectors Jan 07: progress trough 2006, completed by Jan07 testing with comics Trigger commissioning Mar 07: strategy for commissioning in place initial menus, including pre-scales >> emphasis changes from service to physics in 07 Martine Bosman - Group Commitments - IFAE Atlas Dec.21 2005
Group Commitments – Combined Performance gamma+jet Jet reconstruction: calibration/algorithms/effect of Noise,UE,MinBias Underlying Event, Jet multiplicity, QCD measurement; 2006 Tesina Sigrid >> emphasis changes from “Comb.Perf.” to physics in 07 Martine Bosman - Group Commitments - IFAE Atlas Dec.21 2005
Availability for Physics (optimistic!) • New group members: • Imma Riu (R&C); PostDoc 2006; CDF 07-08; student 07 • Maximum Senior/PostDoc time for physics = 0.7 • students evolve from 0.5 to 1 last year Martine Bosman - Group Commitments - IFAE Atlas Dec.21 2005