Colonia Bridges Yap State. February 08, 2006. INTRODUCTION:. Black Micro Corporation (BMC) is submitting a proposal to reconstruct Ganir and the Twin Bridges based upon a more economical & efficient alternate design solution. Existing Project Conditions. Ganir Bridge.

Download Presentation

Colonia Bridges Yap State

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Colonia Bridges Yap State February 08, 2006

  2. INTRODUCTION: Black Micro Corporation (BMC) is submitting a proposal to reconstruct Ganir and the Twin Bridges based upon a more economical & efficient alternate design solution.

  3. Existing Project Conditions Ganir Bridge

  4. Existing Project Conditions Twin Bridge (Donoch)

  5. Proposed Reconstruction – Yap State Design Ganir Bridge

  6. Proposed Reconstruction – Black Micro Design Ganir Bridge

  7. Proposed Reconstruction – Yap State Design Twin Bridge (Donoch)

  8. Proposed Reconstruction – Black Micro Design Twin Bridge (Donoch)

  9. PROJECT COMPARISONS Yap State Design – Black Micro Design

  10. PROJECT COMPARISONS Twin Bridge - Donoch

  11. SCHEDULE OF CONSTRUCTION Yap State Design

  12. 16 Months Nov. 27, 2006 Mar. 18, 2008 Ganir Bridge Nov. 26, 2008 Dec. 26, 2007 Donoch Bridge 11 Months 12 Months Jan. 12, 2009 Feb. 28, 2008 Domathing Bridge 11 Months

  13. SCHEDULE OF CONSTRUCTION Black Micro Design

  14. 9 Months 9 Months Oct. 18, 2007 Oct. 18, 2007 Jan. 31, 2007 Jan. 31, 2007 Ganir Bridge 2 Months Oct. 19, 2007 Aug. 09, 2007 Donoch Bridge 2 Months Oct. 26, 2007 Domathing Bridge 2 Months Oct. 19, 2007 Aug. 09, 2007 2 Months Oct. 26, 2007

  15. SCHEDULE OF CONSTRUCTION Bar Chart

  16. Yap State Design Black Micro Design

  17. SCHEDULE OF QUANTITIES Comparison

  18. SCHEDULE OF PRICE Comparison

  19. DISTINCT FEATURES and PROJECT CONSIDERATIONS

  20. DIFFICULT & COSTLY CONSTRUCTION (Yap State Design) Cofferdams Dewatering Structural Excavation Pile Driving Concrete Pile Caps and Abutments

  21. ENVIRONMENTAL Dewatering Construction Traffic Noise Pollution Quality of Life Stagnation/Water Quality

  22. DURATION OF CONSTRUCTION Traffic Flow Disruption

  23. Yap State Design Black Micro Design