An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. HLT power (CR2) 34th ALICE DCS Workshop • Due to RCU upgrade HLT expects to double computing power • 150kW -> 300kW • Cannot be all UPS (will compete with DAQ) • Proposal HLT: • All Y-racks on UPS (17) • All X,Z-racks on EXD (18) • 5 Z rack as reserve • Estimate per rack: ~9kW (mono) • ~ 15A per phase -> 30A per ‘depart’ • close to limit (32A), needs ‘perfect’ balance over phases • To be discussed with EL

  2. CR2 – alimente depuis nouveau EOD2/20 X01 ( - - ) Y01 (- - ) Z01 ( - - ) X02 ( - - ) Y02 (y01) Z02 ( - - ) 208/20 Y03 (y02) Z03 (z01) X03 ( - - ) 217/20 Y04 (y03) X04 (- - ) Z04 (z02) 209/20 X05 (- - ) Y05 (y04) Z05 (z03) 218/20 X06 ( - - ) Y06 (y05) Z06 (z04) 210/20 X07 (EXD2/20) Y07 (y06) Z07 (z05) 219/20 X08 (x01) Z08 (z06) Y08 (y07) 203/20 211/20 X09 (x02) Y09 (y08) Z09 (z07) 220/20 X10 (x03) Y10 (y09) Z10 (z08) 204/20 212/20 Y11 (y10) X11 (x04) Z11 ( - - ) X12 (x05) Z12 ( - - ) Y12 (y11) 205/20 213/20 Y13 (y12) X13 (x06) Z13 ( - - ) X14 (x07) Z14 (z09) Y14 (y13) 206/20 214/20 221/20 X15 (x08) Y15 (y14) Z15 (z10) Y16 (y15) Z16 (z11) X16 (x09) 207/20 Y17 (y16) X17 (x10) Z17 (z12) 215/20 222/20 Y18 (y17) Z18 (z13)

  3. HLT power (CR2) 34th ALICE DCS Workshop • New cables from new switchboard to new splitter box installed • Splitter boxes not yet installed (but prepared) • Old cabling (EXD, Hazemeyer) still in place

  4. Turbines UX racks 34th ALICE DCS Workshop • Many failures • Fan gets loose from motor • Will need to order 100 pairs • Perform exchange close to racks (limit transport) • Will do a ‘test exchange’ with Fred to estimate time and place needed

  5. 34th ALICE DCS Workshop