1 / 14

LV Cabling 06 Apr 06

LV Cabling 06 Apr 06. Cabling from USC to UXC, Power Distribution. S. Lusin Fermilab / CERN. LV Cabling Issues …. LV Project is responsible for supplying AC power to input of AC/DC converters For CAEN-based systems this means supplying power cabling to detector

Download Presentation

LV Cabling 06 Apr 06

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. LV Cabling 06 Apr 06 • Cabling from USC to UXC, • Power Distribution S. Lusin Fermilab / CERN

  2. LV Cabling Issues … • LV Project is responsible for supplying AC power to input of AC/DC converters • For CAEN-based systems this means supplying power cabling to detector • For Weiner-based systems power is supplied to USC • Power cable chosen is 7x6mm^2, shielded, 23mm dia. • Used for CAEN systems, Weiner systems & service power • Will be CERN stores item • 8 km on order • Primary purpose is for installation in YE1, HF cable chain • Some cable will be available for magnet test • DCS cabling was subdetector responsibility • In the interest of system coherence & installation schedule, ESSC has recently agreed to make DCS cabling design & procurement in cable chains for CAEN-bus systems an LV project responsibility • Financial responsibilities still to be worked out with subsystems • Cable is 50-conductor twisted pair • Ends at detector patch panel • “Standard” CERN stores cable for this purpose is not available in lengths that we need • Alternate cable has been identified, at some cost savings, but needs termination by hand • This should not be a problem. Cable counts are not large.

  3. Cable Selection

  4. Connectors US- UX • Simple, robust design • Can be used by all subsystems • Service power uses similar connector • Smaller insert, prevents cross-plugging • Primary power, service power use same kind of cable • Can be terminated in place

  5. Patch panel connections • Matches 7x6mm^2 cable to 2 or 3 Harting connector outputs • Grounding braid termination not shown • Breakout box design has now been superseded by simple panel

  6. On- Detector (UX-UX) Dist.

  7. Connectors at LVPS end … • Original motivation for quick-connect system was modeled on LV distribution boxes used on standard rack power distribution units • First deliveries of A3486 to B904 had standard three-phase plug (right) • Needed modification to use 16A Harting connector (below) • CMS environment will use 380 and 230V three-phase power • Would like to introduce keying mechanism to prevent cross-plugging of AC-DC converters • Working with POOL to have vendor implement keying

  8. LV breakout boxes • Favored solutions are currently H & J • Needs to be coordinated with CERN POOL & CAEN

  9. Service Power Options • EASY power supplies in hostile area have internal controls that are powered from external source • The external source is located in USC • Original motivation was to provide battery backup for the control circuit in the hostile area • Each EASY module has a control board • Current requirements are: • A3009- 650 mA • All others- 400 mA • Adds up to a substantial current in a long cable Local Cascade

  10. Service power budget • If all service power provided from USC …

  11. Service power budget - Remote • Service power supplies are on-detector …

  12. Cascade Service Power • Total power dissipation in USC is 4.7 KW • Total power dissipation in cables is 308 W • Assumes 10 mm^2 cable pair for ea. Subsystem (for approx. only) • Motivation for cascade power configuration is to minimize impact on shared services

  13. Global LV Partitioning • Main UPS capacity is 1.5 MVA • Contract is finalized, vendor is MGE • Installation design is under way • Six isolation transformers in USC • 300 KVA each, 380V or 230V three-phase, no neutral • Dual electrostatic shields • Have to be partitioned out between subsystems • Cabling imposes additional constraints • No cable can be fed by more than one circuit breaker • One circuit breaker can feed two triplets or three pairs • One distribution cabinet can hold up to 35 circuit breakers • Room for six cabinets available • May need more than that

  14. Proposal for Coordination …

More Related