1 / 18

Rule on Work Zone Safety and Mobility SHA s Road to Compliance

kimimela
Download Presentation

Rule on Work Zone Safety and Mobility SHA s Road to Compliance

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


    1. Rule on Work Zone Safety and Mobility SHA’s Road to Compliance Talking Operations Jawad Paracha March 19, 2007 jparacha@sha.state.md.us

    2. In the Beginning… Summer 2005 Wanted to review the way we do business, not just compliance with the Rule Got a consultant on board to help with review Developed Work Zone Business Plan 12 key focus areas Goals -> Strategies -> Action items Timetable for completion of milestones

    4. Focus on the Rule… Fall 2005 Identified need for communication and coordination within and outside of SHA Developed Temporary Traffic Control Safety and Mobility Council Met as needed to discuss major milestones (significant project, TMP process, etc.)

    5. Focus on the Rule… Winter 2006 – Fall 2006 Worked with a consultant to: Identify Rule requirements (“shalls” vs. “shoulds”) Review existing SHA policies/processes Do they satisfy Rule requirements? Research What are other States doing that is working (or not working)? How does SHA currently incorporate work zone considerations in the project development process? FHWA Guidance Propose and implement new strategies to meet Rule requirements Policies, processes, guidance documents, etc.

    6. Focus on new processes… Winter 2006 – Fall 2006 Worked together with planning, highway, bridge, communications, and construction offices to: Identify current processes for identifying and addressing work zone impacts Identify the level of impact assessment that is completed at each stage project development Discuss areas for improvement and how we can get consideration of work zone impacts moved earlier in the process Incorporate new processes into existing project development process

    7. Focus on new processes… Winter 2006 – Fall 2006 What did we find? Work zone impacts assessment is already a part of the process for what would be “significant projects”, just not a formal, documented process Traffic analysis for work zones has been done on several projects, but not regularly Overall consensus that work zone impacts should be looked at earlier in the process On a conceptual level in project planning On a detailed level during preliminary design (revised as needed as the design progresses to PS&E)

    8. Where did we run into resistance? Identifying responsible persons/ offices to take on additional work load associated with new processes Everyone thinks looking at work zone impacts and developing TMPs are great ideas….BUT resources (man power and funding) to get them done are limited Consensus that consultants will take on most of additional work load; however, there is still effort required on the part of SHA to provide input, review, approve, etc. Districts wanted Design offices to be responsible Design offices wanted the Districts to be responsible Solution: Shared responsibility

    9. Lessons Learned Get buy-in from senior management Decision making and support on policy changes, responsibility distribution, etc. Get input from those who will be doing the work If they are a part of the process, they will be more willing to accept the changes Getting input helps to identify what is “reasonable” change For example, our proposed alternatives analysis process was modified to include two levels – a concept level during planning and a detailed level during design – based on input from an info session held with staff in the Office of Planning

    10. Compliance! Notification of compliance received January 2007

    11. Where are we headed? Implementation process Include TMPs with all significant projects that are advertised after October 2007 to the extent feasible Provide training to design and District offices on new policies and processes Develop “blanket exceptions” for projects that are classified as significant by FHWA’s more than 3 day lane closure requirement, but are not considered significant by SHA

    12. SHA’s TMP Process Planning, Preliminary Investigation and Design Step 1 – Create TMP Team Step 2 – Compile Project Material Step 3 – Maintenance of Traffic Red Flag Summary Step 4 – Identify Significant Projects Step 5 – Maintenance of Traffic Alternative Analysis (MOTAA) Step 6 – Determine TMP Needs Step 7 – Identify Stakeholders and Revise TMP Team Step 8 – Preliminary Design (Draft TMP) Step 9 – Detailed Design (Semi-final, final TMP)

    13. SHA’s TMP Process Construction Step 10 – Implement TMP Step 11 – Monitor TMP Step 12 – Update/Revise TMP Performance Assessment Step 13 - Evaluation

    14. Defining Significant Projects 6+ months of discussion on Significant Projects Developed smaller working group with representatives from Districts, design and planning offices Presented for comment several times with TTC Safety and Mobility Council Quantitative definition did not seem to fit Smaller $ projects may still have significant work zone impacts or require additional coordination Qualitative approach seemed to work best Allows for engineering judgment to play a role

    15. Defining Significant Projects Developed 2 flow charts OPPE, OHD, OBD (Planning and Design Offices) District and minor projects Major criteria include Project location Anticipated mobility and safety impacts Project and/or work zone characteristics If the project is identified as a Significant Project, perform Maintenance of Traffic Alternatives Analysis (MOTAA) to try identify a solution to reduce impacts below thresholds IF MOTAA does not identify a solution that reduces impacts, develop Transportation Management Plan

    18. QUESTIONS? Contact: Jawad Paracha Email: jparacha@sha.state.md.us Phone: 410-787-5891

More Related