E N D
1. Rule on Work Zone Safety and MobilitySHA’s Road to Compliance Talking Operations Jawad Paracha
March 19, 2007 jparacha@sha.state.md.us
2. In the Beginning…Summer 2005 Wanted to review the way we do business, not just compliance with the Rule
Got a consultant on board to help with review
Developed Work Zone Business Plan
12 key focus areas
Goals -> Strategies -> Action items
Timetable for completion of milestones
4. Focus on the Rule…Fall 2005 Identified need for communication and coordination within and outside of SHA
Developed Temporary Traffic Control Safety and Mobility Council
Met as needed to discuss major milestones (significant project, TMP process, etc.)
5. Focus on the Rule…Winter 2006 – Fall 2006 Worked with a consultant to:
Identify Rule requirements (“shalls” vs. “shoulds”)
Review existing SHA policies/processes
Do they satisfy Rule requirements?
Research
What are other States doing that is working (or not working)?
How does SHA currently incorporate work zone considerations in the project development process?
FHWA Guidance
Propose and implement new strategies to meet Rule requirements
Policies, processes, guidance documents, etc.
6. Focus on new processes…Winter 2006 – Fall 2006 Worked together with planning, highway, bridge, communications, and construction offices to:
Identify current processes for identifying and addressing work zone impacts
Identify the level of impact assessment that is completed at each stage project development
Discuss areas for improvement and how we can get consideration of work zone impacts moved earlier in the process
Incorporate new processes into existing project development process
7. Focus on new processes…Winter 2006 – Fall 2006 What did we find?
Work zone impacts assessment is already a part of the process for what would be “significant projects”, just not a formal, documented process
Traffic analysis for work zones has been done on several projects, but not regularly
Overall consensus that work zone impacts should be looked at earlier in the process
On a conceptual level in project planning
On a detailed level during preliminary design (revised as needed as the design progresses to PS&E)
8. Where did we run into resistance? Identifying responsible persons/ offices to take on additional work load associated with new processes
Everyone thinks looking at work zone impacts and developing TMPs are great ideas….BUT resources (man power and funding) to get them done are limited
Consensus that consultants will take on most of additional work load; however, there is still effort required on the part of SHA to provide input, review, approve, etc.
Districts wanted Design offices to be responsible
Design offices wanted the Districts to be responsible
Solution: Shared responsibility
9. Lessons Learned Get buy-in from senior management
Decision making and support on policy changes, responsibility distribution, etc.
Get input from those who will be doing the work
If they are a part of the process, they will be more willing to accept the changes
Getting input helps to identify what is “reasonable” change
For example, our proposed alternatives analysis process was modified to include two levels – a concept level during planning and a detailed level during design – based on input from an info session held with staff in the Office of Planning
10. Compliance! Notification of compliance received January 2007
11. Where are we headed? Implementation process
Include TMPs with all significant projects that are advertised after October 2007 to the extent feasible
Provide training to design and District offices on new policies and processes
Develop “blanket exceptions” for projects that are classified as significant by FHWA’s more than 3 day lane closure requirement, but are not considered significant by SHA
12. SHA’s TMP Process Planning, Preliminary Investigation and Design
Step 1 – Create TMP Team
Step 2 – Compile Project Material
Step 3 – Maintenance of Traffic Red Flag Summary
Step 4 – Identify Significant Projects
Step 5 – Maintenance of Traffic Alternative Analysis (MOTAA)
Step 6 – Determine TMP Needs
Step 7 – Identify Stakeholders and Revise TMP Team
Step 8 – Preliminary Design (Draft TMP)
Step 9 – Detailed Design (Semi-final, final TMP)
13. SHA’s TMP Process Construction
Step 10 – Implement TMP
Step 11 – Monitor TMP
Step 12 – Update/Revise TMP
Performance Assessment
Step 13 - Evaluation
14. Defining Significant Projects 6+ months of discussion on Significant Projects
Developed smaller working group with representatives from Districts, design and planning offices
Presented for comment several times with TTC Safety and Mobility Council
Quantitative definition did not seem to fit
Smaller $ projects may still have significant work zone impacts or require additional coordination
Qualitative approach seemed to work best
Allows for engineering judgment to play a role
15. Defining Significant Projects Developed 2 flow charts
OPPE, OHD, OBD (Planning and Design Offices)
District and minor projects
Major criteria include
Project location
Anticipated mobility and safety impacts
Project and/or work zone characteristics
If the project is identified as a Significant Project, perform Maintenance of Traffic Alternatives Analysis (MOTAA) to try identify a solution to reduce impacts below thresholds
IF MOTAA does not identify a solution that reduces impacts, develop Transportation Management Plan
18. QUESTIONS?Contact:Jawad ParachaEmail: jparacha@sha.state.md.usPhone: 410-787-5891