West Haymarket redevelopment projects. Project Status Update November 2nd, 2012. West Haymarket Local Participation Report All Workers – Including Engineering and Professional Services Through September / October 2012.
E N D
West Haymarket redevelopment projects Project Status Update November 2nd, 2012
West Haymarket Local Participation ReportAll Workers – Including Engineering and Professional ServicesThrough September / October 2012
West Haymarket Local Participation ReportDavis Bacon / Construction EmployeesThrough September / October 2012
West HaymarketCompany Participation $140 Million Nebraska Dollars out of $193 Million
NEW PINNACLE BANK ARENA DRIVE, LOOKING NORTH FROM “Q” STREET
WATER MAIN CONSTRUCTION NEAR “N” STREET AND PINNACLE ARENA DRIVE
Presentation to the JPA November 2, 2012
Safety • Worked 141 consecutive days without a safety incident • The Project averages over 250 Craft Workers daily
Concrete Superstructure • The concrete work continues with Slab on Grade and Slab on Metal Deck • Garage Foundations have been poured, work continues on Garage walls
Milestones Achieved • 1st Phase of structural precast is complete • All four long span trusses are installed • 50% of Metal Deck Installed • Roofing Installation started • Metal Panel Installation started • Curtainwall Installation started