An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. West Haymarket redevelopment projects Project Status Update July 12, 2013

  2. West Haymarket Local Participation ReportAll Workers – Including Engineering and Professional ServicesThrough June2013

  3. West Haymarket Local Participation ReportDavis Bacon / Construction EmployeesThrough June2013

  4. West HaymarketCompany Participation Approx. $161 Million Nebraska Dollars out of $226 Million

  5. Infrastructure Progress

  6. FESTIVAL AREA PARKING LOT & START OF STAIRWAY CONSTRUCTION

  7. RENOVATED CANOPY GETTING ITS NEW ROOF INSTALLED

  8. SILVA CELL CONSTRUCTION ALONG SOUTH SIDE OF “R” STREET

  9. STREETSCAPE WORK AT SALT CREEK ROUNDABOUTS

  10. VIEW DOWN CANOPY STREET FROM THE ARENA

  11. WH PARKING DECK #1 PARKING EQUIPMENT INSTALLED

  12. DECK #1 PAINTED PARKING STALLS

  13. LOOKING SOUTHEAST FROM DECK #1

  14. VIEW LOOKING EAST DOWN THE NEWLY POURED “Q” STREET

  15. DEC SOUTH EXTENSION PIPING PROGRESS

  16. AERIAL 6-17-2013

  17. AERIAL6-17-2013

  18. Presentation to the JPA July 12, 2013

  19. Milestones Achieved • Ice floor test successful • Premium level is complete • Systems testing progressing • Exterior lighting installed • Site signage installation • Site paving nearing completion • Garage concrete complete • Final punch list started

  20. Safety • Worked 185 consecutive days without a safety incident • The Project averages over 200 Craft Workers daily • 1 incident in last 402 days

  21. Seat Installation

  22. Ribbon board

  23. Ice floor test successful

  24. Architect punch process

  25. Terrazzo flooring

  26. Terrazzo flooring prep

  27. Main concourse finishes

  28. Premium level finishes

  29. Completed Suites

  30. Garage entrance

  31. Site signage

  32. Site finishes and paving

  33. Building lighting