VTPO Board Introduction to US 1 Corridor Improvement Program Phase II . September 25, 2012. Phase II Builds Off of Phase I. Phase I products US 1 project database Identified need for improvement of multi-modal trip-making 18 month schedule US 1 from Brevard County to Flagler County.
E N D
VTPO Board Introduction to US 1 Corridor Improvement Program Phase II September 25, 2012
Phase II Builds Off of Phase I • Phase I products • US 1 project database • Identified need for improvement of multi-modal trip-making • 18 month schedule • US 1 from Brevard County to Flagler County
Phase II Objectives • Understand the current and future travel patterns along US 1 • Identify the vision for the corridor • Outline a strategic approach to accomplish the vision and mobility goals • Identify specific action items, their prioritization and timing, and potential funding mechanisms.
Next Steps • Collect and analyze multi-modal transportation and land use data • Conduct stakeholder interviews • Develop a project working group