1 / 10

Cost Projection

Cost Projection. Costs are planned, measured, analyzed and controlled in terms of project activities. Expenditure for any activity is incurred evenly over the duration of the activity. Budgeted cost of the activity is earned value.

koto
Download Presentation

Cost Projection

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Cost Projection • Costs are planned, measured, analyzed and controlled in terms of project activities. • Expenditure for any activity is incurred evenly over the duration of the activity. • Budgeted cost of the activity is earned value. • When activity is complete it is assumed to earn value for project equivalent to its budgeted cost. • Project progresses track is kept of actual value earned and also actual cost.

  2. Earned value Analysis Provides an analytical framework for project control by estimating factors like cost variance, schedule variance, cost performance index, estimated cost performance index It is the % of the total cost budgeted against the total cost incurred

  3. In case Actual Expenditure incurred for completion of an activity exceeds its budgeted cost, the project does not earn any additional benefit since activity parameters are well specified. The variance indicated cost over-run

  4. Budgeted Cost for Work scheduled (BCWS) Value of the work that should have been completed as of the date of review.

  5. Budgeted Cost for Work Performed (BCWP) Budgeted cost for completed work.

  6. Actual Cost for work performed (ACWP) It is cost actually expended in completing the work accomplished within a given time period

  7. Budgeted Cost for Total Work (BCTW) It is total budgeted cost for the entire project

  8. Additional Cost for completion (ACC) It is the estimated additional cost required for completing the project

  9. Performance Indicators • CV= ACWP – BCWP Cost Variance • CPI = BCWP / ACWP Cost Performance Index • SV = BCWP – BCWS Schedule Variance • SPI = BCWP / BCWS Schedule Performance Index • TV = (Date of Review) – (Date on which BCWP = BCWS) Time Variance • ECP Index = BCTW /(ACWP + ACC) Estimated cost of performance index

  10. Cost over – run ->When the cost incurred is more than the value of work done. • Cost under – run -> When the cost incurred is less than the value of work done. • CV <1 = cost over run • Time over-run -> project is behind schedule • Time under-run -> project is ahead of schedule SV <1 = time over run

More Related