Harnessing the energy of biogas Dr Leonid Itskovich Energy Manager Energy Awareness Week, Christchurch, May 2010
Harnessing the energy of biogas • 1980s: Christchurch Wastewater Treatment Plant • 2007: QEII • 2010: Christchurch Art Gallery • 2010: WWTP Biosolids Dryer • 2010: New Civic Building
Biogas utilisation efficiency • gas escaping to atmosphere • flare • heating fuel • co-generation (electricity+heat) • tri-generation (electricity+heat+refrigeration) • city-wide bio-energy system!
Digester Gas utilisation • 730 m3 of gas per hour • 63% methane • compressed gas - fuel for Council’s vehicles (1983-1994) • electricity and heat generation since 1996 • 11,000,000 kWh per annum of electricity
Burwood Landfill • 90 hectares • Up to 25 m deep • Up to 264,000 tonnes of refuse per year • 60% organic waste • Operated 1984 – 2005
Landfill Gas • 1000 m3 of gas per hour • 50-60% methane • Methane - a powerful greenhouse gas with 22 times more impact on climate change than carbon dioxide.
Directional drilling for 18-kilometre gas pipeline Burwood Landfill - QEII – WWTP – New Civic – Art Gallery
Gas pipeline Treatment plant & flare • Burwood Landfill • 90 hectares • Up to 25 m deep • Up to 264,000 tonnes of refuse per year • 60% organic waste • Operated 1984 – 2005
Landfill gas utilisation at QEII QEII Burwood Landfill Boiler 2 Flare Underground gas pipeline 3.7 km Boiler 1 Heat and electricity used in QEII sports centre Pipeline Cogeneration Fan 15 gas collection wells Condensate collected & returned to landfill Gas chiller & condensate collection Pipeline to WWTP Landfill Gas Collection Gas Treatment Gas Transport Gas Combustion
Burwood Landfill Gas Treatment Plant Compressors Blast chiller Flare Fan Inward gas pipe Controls Chillers Controls Condensate collectors
Landfill gas co-generation engine at QEII
Under construction: biogas boiler for biosolids dryer at WWTP
Under construction:Biogas and wood chip boilers for biosolids dryer at WWTP
Absorption chiller – part of Tri-generation plant at New Civic building
Biogas projects: benefits • replaces 2.1 million litres of LPG each year (fossil fuel) • replaces 16 million kWh of electricity from grid pa • saves city ratepayers $3M each year in energy costs • carbon credits sold to British Gas ($4M) • better environment • the landfill can more easily be re-vegetated because the landfill gas that damages plant roots is captured.
Acknowledgement of expertise and assistance • BECA • Powell Fenwick Consultants • Rockgas (Contact Energy) • Energy For Industry (Meridian Energy) • EECA • Contractors and equipment Suppliers