An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Wind policies in Italy Gianni Silvestrini Advisor to the Ministry of Economic Development Ewec, Milan, 7 may 2007

  2. The wind situation: moderate growth, with possible acceleration • Average new installations in 2004-6: 450 MW/year • Total power 2006: 2.123 MW • Total electricity generated: 3,2 TWh/y (1% total consumption) • Estimate for 2007: 2.800 MW • Estimate for 2012: 5.000 – 8.000 MW

  3. Wind power in Italian regions 2,5 Total installed 2.123 MW 3,5 6,5 (1,7) Installed in 2006 417 MW 28 (26) 1,5 155 9 70 (19) 460 (120) 417 (8) 346 (12) 153 (68) 7 (7) 452 (142)

  4. Share of wind turbines by manufactures (end of 2006)

  5. Wind operators in Italy

  6. Evolution of the wind turbines size

  7. Industrial development • Vestas Italia: 440 MW produced in 2006 (60% exported in China) • A couple of new companies intend to go to the market • Emerging companies of small size turbines (< 20 kW)

  8. Present incentives scheme very favourable • Compulsory RES electricity quota (in 2007 3,05 %) • Value of green certificates issued for the 2006 production: 125 €/MWh • Green certificates valid for 12 years • Moreover: Sale of electricity at 60-80 €/MWh…

  9. Problems still open • Undefined situation of tariffs in the medium term • Lenghty authorization process • Hostility by some Region • Cases of delays in interconnections

  10. New policy directions • New law in discussion to be adopted in 2007: - New tariff structure (feed-in scheme for small plants; still in discussion for large turbines) - New simpler authorization process - Possibility to overcome Regions blocks - Clearer conditions for grid connection

  11. Other actions • Interministerial guidelines on siting • Definition of new targets for 2012 (Del. Cipe 2007) • “Industry 2015 law”: creation of an Italian renewable industry (350 M€, coupled with 2.3 billions € of European funds)