1 / 23

Fuel Flexibility with Biomass for Coal Boilers at University of Iowa

Fuel Flexibility with Biomass for Coal Boilers at University of Iowa. Ben Anderson – University of Iowa Andy Ungerman – Stanley Consultants. Agenda. Introductions Overview & Biomass Initiatives Permitting Strategy Project Design & Biomass Considerations Project Construction

lacy-buck
Download Presentation

Fuel Flexibility with Biomass for Coal Boilers at University of Iowa

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Fuel Flexibility with Biomass for Coal Boilers at University of Iowa Ben Anderson – University of Iowa Andy Ungerman – Stanley Consultants

  2. Agenda • Introductions • Overview & Biomass Initiatives • Permitting Strategy • Project Design & Biomass Considerations • Project Construction • Startup & Lessons Learned • Future Plans • Conclusions & Questions

  3. Introductions • Ben Anderson – University of Iowa • Power Plant Maintenance & Engineering Manager • BSME from Iowa State University • Petro-chemical background • Andy Ungerman - Stanley Consultants • Mechanical Engineer – Energy Business Group • BS & MSME from Iowa State University • Power Plant Consulting Background

  4. Overview • University of Iowa – Main Power Plant • 4 Boilers: 600+ klb/hr, 3 Turbine Generators - 24.7 MW • 6 offsite natural gas and 1 biomass boilers 135,00 lbs/hr 140,00 lbs/hr

  5. Biomass Initiative • University of Iowa - Biomass Initiative • Achieve the goal of 40% renewable energy consumption on the campus by 2020 • More info at http://sustainability.uiowa.edu/biomass/

  6. Permitting Strategy • BLR 10 Biomass • IDNR to issue permit on 12/2011, failed PM 10 test, permit closed • New permit submitted several months ago • Wood chips, yard trimmings, paper sludge – Cedar Rapids Landfill & other local sources • Update with Fuel grasses – miscanthus • Expect approval in next month • Increased reporting • Track fuels usage • Frequent fuel sampling (ensure below PSD for NOx, SO2, and PM2.5) • BLR 11 Biomass • Current permit for oat hulls • Approved variance to burn wood chips • Collaboration with state park to dispose of 2500 tons of pine • Plan to have permanent change submitted in early February • Plant wide Applicability Permit (PAL) submitted to IDNR

  7. Project Design - Overview • Replace “dense” phase coal handling system with 30 TPH belt conveyor • Provide provisions for future biomass or PRB • Original plant – 1926 • 3D scan converted to 3D Model

  8. Project Design - Overview Compact, cartridge dust collectors ~16° incline, tubular gallery 75 ton bunker (8 hr supply) Equipment located for future biomass equipment Completely insulated enclosures and galleries Extensive reinforcement and modification to existing structures Gravimetric feeder w/ conical distributor

  9. Project Design: Co-firing with Biomass • UT Distributors for Biomass • Woodchip/Biomass issues – non uniform sizing1 • Volumetrically limited – Max 15% Biomass (soft number) – assuming sizing is similar1 • 15% vol blend = 6% by weight = 3% by BTU (assuming woodchip density of 20 lb/ft3, and a heating value of 4,500 Btu/ft3) • Closer the properties to coal, higher the percent1 – 100%? • Pelletized or torrifiedwood etc. • Non-Segregated Distributor • Woodchip/biomass issues – non uniform sizing • Different sizing may lead to segregation • Lack of data on biomass • Closer properties are to coal, the better • 1Per information received from Detroit Stoker Corp, used with permission.

  10. Project Design: Co-firing with Biomass with Stoker Boiler • Best Arrangements for Co-Firing Wood1 • Separate fuel trains • Different fuel sizing = separate trains • Goal is to get good ash bed on grate and uniform distribution • Symmetry is important! UTs 1 and 5 or 2 and 4 • Combo Feeders1 • 1000 lbs/in of feeder (Qty 2 feeders = 54 kpph) • Recommended fuel drop height = 10 ft • Distributes fuel lower in furnace (preferred) • Requires header to be moved • Air swept spouts1 • 50% of grate to be covered with spouts (20’ grate requires four 30” air spouts) • Location = higher in furnace • Tube bending vs. moving header • Must get around non-seg distributor • 1Per information received from Detroit Stoker Corp, used with permission. Air swept spouts Combo Feeders

  11. Future Biomass Flexibility at UOI • Unique design – grav. feeder w/ non-seg dist. • 75 ton (coal) bunker can be offset further compared to batch-type feeder. • Allows emergency unloading • Future biomass robbing screws and hoppers can be fed by a “surge bin” fed from a separate material handling system using a new silo • Detroit Stoker UT Distributor hoppers modified to allow for future Combo feeders. • Bunker could be modified to bottom reclaim (remove bottom cone) 75 Ton Bunker Drag chain Surge hoppers & robbing screws Future Feeder/Non Seg Offset UT hoppers allow for future Combo feeders.

  12. Comparison of Fuels and Mat’l Handling for Boiler 10 * Heat input and Heating value taken from Biomass Conversion Study Report (2010) for UOI by Riley Power. Used with Permission.

  13. Project Construction • Logistics • Equipment Fabrication • Crane - Gallery & Conveyor install • Boiler Shutdown and Dense Phase Demo • Start-up & Lessons Learned

  14. Project Construction – Logistics • Iowa River • Campus Location • Space Constraints • Equipment laydown • Contractors

  15. Project Construction – Equipment Fabrication • Schedules • Manufacturing visits • Delivery

  16. Project Construction - Crane • Logistics – 20+ semi tucks • Ground survey • Voids • Flat surface • Crane location & continued plant ops

  17. Project Construction - Installation

  18. Project Construction - Installation

  19. Project Construction - Boiler Shutdown & Dense Phase Demo • Major 3+ month outage • Boiler maintenance • Boiler lay-up • Planned start-up on 11/30/12 • Back-up boiler installed

  20. Start-up & Lessons Learned • Permitting & Construction Timing • Commissioning & Training • CHS operational - several nuisance trips • Alignment switches; belt tracking • CO monitors • VFD Fault on gravimetric feeder • Plugged conveyor • Alarm Rationalization (CO, Alignment switches) • Cleanliness

  21. Future Plans • Full inspection and baseline on boiler (complete) • Burn wood chips in near future (ASAP) • Begin developing test runs for other fuels (Ongoing) • Installing natural gas burner Spring 2013 • Internal inspection at regular intervals (Ongoing) • Modifications to fuel handling system for increased Biomass combustion

  22. Conclusions • Develop solid Biomass plan • Design projects to be flexible for future conversions • Work on permitting strategy early and plan for good discussions • Complete equipment scenario/what-if analysis and implement into planning/design

  23. Questions

More Related