40 likes | 240 Views
Russell Cave Elementary – Renovation. Architect: Pearson & Peters Architects General Contractor: Congleton-Hacker Construction Substantial Completion Date: August, 2010 GC Contract Sum: $5,001,150 Total Project Cost: $6,103,400 Change Orders to Date (2): $11,180
E N D
Russell Cave Elementary – Renovation Architect: Pearson & Peters Architects General Contractor: Congleton-Hacker Construction Substantial Completion Date: August, 2010 GC Contract Sum: $5,001,150 Total Project Cost: $6,103,400 Change Orders to Date (2): $11,180 Current Phase: 1 (On Schedule) Estimated Completion: 42% September 2009
Russell Cave Elementary – Renovation Rendering of Final Façade September 2009
Russell Cave Elementary – Renovation Work Completed in Last 30 Days: Roof at new addition is complete and the addition is dried in. Renovation of (4) classrooms on the south side continues, demolition is complete, new mechanical and electrical rough-in is in process. Stone veneer on addition base is in process. New windows have been installed at (4) classroom renovation. Current Work Effort (September): Interior ramp and stair in new addition will be poured. New horizontal blinds will be installed in cafeteria. Framing for knee walls at new windows and soffits in renovated classrooms will be installed. Block filler and painting will begin. New floor material will be delivered the first week of September Demolition of the general construction items will begin in the gymnasium. September 2009
Russell Cave Elementary – Renovation New Classroom Windows New Media Center Interior of Cafeteria New Kitchen September 2009