Follow up on option 3c: New Evacuation Gallery Work method, Schedule, Cost, Implications for CMS

Follow up on option 3c: New Evacuation Gallery Work method, Schedule, Cost, Implications for CMS. Contributions from. BE -ABP -ASR -BI -CO. DG -RP. GS -SEM -ASE. IT -CS. PH -CMX. TE -CRG -EPC -MPE. EN -CV -EL -MEF

lang
Download Presentation

Follow up on option 3c: New Evacuation Gallery Work method, Schedule, Cost, Implications for CMS

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Follow up on option 3c: New Evacuation GalleryWork method, Schedule, Cost, Implications for CMS Contributions from BE -ABP -ASR -BI -CO DG -RP GS -SEM -ASE IT -CS PH -CMX TE -CRG -EPC -MPE EN -CV -EL -MEF -STI martin.gastal@cern.ch

  2. Method of work and draft schedule • Week 1 & 2 • CE set up time - impact on CMS only • Includes metallic platform installation, ventilation system for dust extraction, tooling installation, temporary power cables, dust screen. Loading platform martin.gastal@cern.ch

  3. Method of work and draft schedule • Week 1 & 2 • Removal of services in UJ56 – “Eau Brute” water piping (~1week if prepared), CV equipment (1week), BRAN gas bottles… martin.gastal@cern.ch

  4. Method of work and draft schedule • Week 3 & 4: • Excavation phase – Impact only on CMS – no work on the –Z end of the UXC55 • Removal of services in UJ56 – water piping, CV equipment… To UXC55 martin.gastal@cern.ch

  5. Method of work and draft schedule • Week 5& 6: • Excavation phase – Impact both on CMS and UJ56 Second crew To UXC55 martin.gastal@cern.ch

  6. Method of work and draft schedule • Week 7,8,9 & 10: • 4 weeks of lining - impact on both CMS and UJ56 • Shuttering, concrete pipe through the PX56, paint… martin.gastal@cern.ch

  7. Method of work and draft schedule • Week 11 and 12: • 2 weeks of clean up - impact on both CMS and UJ56 • Removal of metallic platform in UXC55 martin.gastal@cern.ch

  8. Method of work and draft schedule • Week 13 onwards: • Installation of blast door ~10kCHF • Installation of a sector door in new gallery (move from UJ561) • 1st draft estimate: ~60CHF mainly driven by software modification and commissioning • Installation of lighting • Modification of ventilation martin.gastal@cern.ch

  9. Additional considerations • Error margin on time estimates for CE work • +/-20%, • Potential sources of delay • Difficult dust management • Services not dismantled in time in UJ56 • Unforeseen access restrictions • Unexpected water inflow from PM54, unforeseen geological conditions martin.gastal@cern.ch

  10. Additional considerations • Error margin on cost estimates for CE work • 800,000CHF +/-30%, • Use of PM56: to be used for CE personnel access • Potential RP issues • S Roesler: The design should not compromise the non designated area status of the USC55, especially since the geometry would allow to add shielding • Getting simulations to back this statement would take 1 month of a fellow…. Once this gallery becomes part of the baseline solution, the resources for the necessary verification will be found, if necessary, with financial help by Christoph martin.gastal@cern.ch

  11. Impact on CMS • During the 2012 shutdown CMS will have to be fully open to allow the servicing of the PIX • -Z end draft sequence already very challenging. • 12 weeks of delay would have to be included. • Significant overhead martin.gastal@cern.ch

  12. Pros and Cons • Cons: • Non negligible cost • 12 weeks of delay on the CMS schedule • Significant disruption to the CMS Experimental area during work • Pros: • Faster and safer emergency evacuation • Allow using the UJ561 for R2E or upgrade projects • In line with initial and approved evacuation scheme (Christoph Schaefer) martin.gastal@cern.ch

  13. Reserve Slide J Bos PH-CMX 6.92m CV equipment To relocate for R2E BRAN Gas Can be moved martin.gastal@cern.ch

  14. Reserve Slide New blast door martin.gastal@cern.ch J Bos PH-CMX

  15. Reserve Slide • EN-EL work: ~ CHFM2.3 • Not including work to be done by other service groups contributing to the relocation of EN-EL equipment • GS-SEM work: • Escape gallery: < CHFM1 • Service ducts: CHF4,000/m • E.g: 15m link between UJ56 and bypass = CHF60,000 • Costs of fire doors, smoke detection, metallic structures, cooling and ventilation, re-commissioning still not assessed martin.gastal@cern.ch