Tracking Ops Reserve Charges. DA Demand > RT Demand All DA units dispatched according to DA awards but do not have an incentive to run in RT; RT units are not dispatched; DA units buy back energy not generated at RT LMP; No additional Operating Reserve costs incurred. DA Demand < RT Demand
E N D
Tracking Ops Reserve Charges • DA Demand > RT Demand • All DA units dispatched according to DA awards but do not have an incentive to run in RT; • RT units are not dispatched; • DA units buy back energy not generated at RT LMP; • No additional Operating Reserve costs incurred. • DA Demand < RT Demand • In RT, all DA units dispatched according to DA awards at levels equal to or greater than awarded; • Additional units are dispatched in RT as well; • Potential RT Operating Reserve costs incurred. • DA Demand = RT Demand • All DA units dispatched according to DA awards.