An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Y2K at Andrews University Status Report to the Risk Management Committee 13-May-1999

  2. Presidential Task Force • Eight members, representing the areas of: • financial administration and institutions, • academic concerns, including laboratories, • plant and equipment, • networks, servers and personal computers, • all administrative systems • Has met at least monthly since June, 1998 • Web site: Andrews University Y2K Web Site

  3. Phases of the Action Plan 1. Awareness 2. Inventory Phase 3. Assessment and Planning Phase 4. Conversion/Replacement Phase 5. Validation and Deployment Phase

  4. What have we done? Hired a Y2K Coordinator on contract 1.1 Familiarized with Y2K issues 1.2 Delivered Y2K awareness presentations 2.1 Researched Y2K tracking solutions 2.2 Developed a tracking package in-house 2.3 Documented COBOL programs still in use 3.1 Developed a project plan and schedule

  5. Results of PC Testing • 800 PCs were tested last summer (75%) • Data for ~50% has been collected via web • Projection: 300+ PCs will fail in year 2000 • Capital replacement costs: • $1,000 per system • $150 to $300 per monitor • Labor & software costs: $90 per machine

  6. Compliancy Status Report Total Reported: 572

  7. Where are we now? • Our web-based tracking software has been deployed • Departmental Y2K Coordinators are collecting and submitting data • Y2K Task Force members are working on Y2K issues in their areas • Vendors & other institutions are being worked with • Plant is being inventoried and remediation plans made • Banner is compliant (since Thanksgiving) • COBOL programs are being converted • Further training is in progress • Bulk PC purchase plans are being finalized • Groups are working on contingency plans

  8. What’s next? • Refine analysis of inventory once collected • Continue to encourage Departmental Coordinators • Determine impact and priorities • Plan and implement repairs/replacements • Plan and test contingency plans

  9. The Millennium Bug • It is being overplayed and underplayed • But there is also a stern reality • The Millennium Bug • Andrews University Y2K Web Site