E-rate Selection Process. RFI/RFP Documents Developed Vendor Conference Initial Submissions First Review Mistake Addendum Second Review Recommendations Local Vendor Participation Next Steps. RFI/RFP Documents. RFI/RFP Documents Developed Vendor Qualification
E N D
E-rate Selection Process • RFI/RFP Documents Developed • Vendor Conference • Initial Submissions • First Review • Mistake • Addendum • Second Review • Recommendations • Local Vendor Participation • Next Steps
RFI/RFP Documents • RFI/RFP Documents Developed • Vendor Qualification • Internal Wiring and Network Configuration • LAN Maintenance • Classroom Counts by Sites • Six RFI’s for Internal Wiring (5-7 Schools Each) • One RFI for LAN Maintenance (52 Schools)
Vendor Conference • 12/12/02 – Two Hour Vendor’s Conference • Process described to 35 vendors from 22 companies • Extensive Q&A (Proceedings audio recorded) • Vendor contact information gathered • All documents, including vendor contact list posted on-line • E-mail list for vendor questions established. Answers available to ALL vendors • 12/13/02 & 12/16/02 Site walks to ALL sites
Initial Submissions • Responses due 1/2/03 (extended from 12/27/02) • Initial Submissions Reviewed by Tech Services, Facilities, and Purchasing • 11 responses to Internal Wiring RFI/RFPs • 6 responses to LAN Maintenance RFI/RFP
First Review • Vendors screened for qualifications and responsiveness to RFI • 5 responses to Internal Wiring RFI/RFPs eliminated for non-compliance • 3 responses to LAN Maintenance RFI/RFP eliminated for non-compliance • Remaining responses reviewed and ranked based on technical design and cost.
Mistake in Form 470 • District is informed by vendor that our Form 470 may contain error • SLD contacted. District advised to re-submit Form 470 for Internal Connections • 1/8/03 Revised Form 470 submitted • New 28 day window begins • Additional vendors free to submit, existing vendors can modify proposals.
Addendum to RFI/RFP • 1/10/03 - addendum to RFI/RFP developed, e-mailed to all current respondents and posted on website. Additional site walks conducted. • Clarifies conditions for acceptable responses • Designed to improve quality of responses • Allow non-responsive vendors to modify response • Builds in additional protections and quality control for District
Second Review • 10 responses to Internal Wiring RFI/RFPs (1 eliminated as non-responsive). No new vendors submitted in 2nd round. • Responses to all RFI/RFPs are screened as before for technical design and cost • 4 finalists for RFI/RFP 1-6 and 2 finalists for RFI/RFP 7 identified and asked follow-up questions. • 1/28/03 – 2 of 4 finalists for RFI/RFP voluntarily withdrawn. • 1/29/03 - Review committee’s recommendations given to District leadership
Changes to Process Resulted In: • Enabling Local Vendors to act as Primaries • Significant Increase in Local Participation • Increase in collaboration and integration between OUSD Departments. • Increased competition = Reduced cost to OUSD • After final negotiations, we expect the work come under expected costs by approximately 20%.
Next Steps • Sign LOIs with Vendors • Submit 471 (By Thursday Night) • Finalize Agreements with Vendors including Management Structure and Oversight. • Notification of Award Expected in Late Spring