1 / 17

District 2 System Preservation Projects for FY 14 and FY 15

District 2 System Preservation Projects for FY 14 and FY 15. Gregory B. Holsey - District Engineer Thomas S. Revelle - Assistant District Engineer – Project Development.

leigh
Download Presentation

District 2 System Preservation Projects for FY 14 and FY 15

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. District 2 System Preservation Projects for FY 14 and FY 15 Gregory B. Holsey - District Engineer Thomas S. Revelle - Assistant District Engineer – Project Development

  2. Contract No. - XY4145177Various Locations in Kent CountyResurfacingAdvertisement Date: November 1, 2013Notice to Proceed: January 6, 2014Approximate Hot Mix Asphalt Tonnage: 35,300 Tons.MD 291 from East of MD 213 to Morgnec Cutoff Road; MD 291 from MD 701 to Daisy Drive; MD 444 from End of SHA Maintenance to MD 444; MD 298 from MD 213 to MD 292 MD 444 MD 291

  3. Contract No. - XY4175177Various Locations in Queen Anne’s CountyResurfacingAdvertisement Date: November 1, 2013Notice to Proceed: January 13, 2014Approximate Hot Mix Asphalt Tonnage: 34,850 TonsMD 18V from MD 18B to Structure #17048; MD 300A from U.S. 301 to MD 19; MD 290 from MD 544 to MD 300; MD 404 from Talbot County Line to Caroline County Line; MD 662 from Talbot County Line to U.S. 50, MD 18C in Queenstown Town Limits MD 662 MD 300A

  4. Contract No. - AW8965270MD 404 from West of MD 309 to Cemetery Road – Phase 1-B4 Lane Divided Highway ConstructionAdvertisement Date: November 29, 2013Notice to Proceed: February 10, 2014Approximate Hot Mix Asphalt Tonnage: 43,000 Tons

  5. Contract No. - CE29351807 Existing Bridges on U.S. 1, U.S. 40, MD 222 and MD 272Clean/Paint BridgesAdvertisement Date: November 29, 2013Notice to Proceed: February 10, 2014U.S. 1 over Branch of Octoraro Creek, U.S. 40 Over North East Creek, U.S. 40 Over Little North East Creek, U.S. 222 Over Octoraro Creek, MD 272 Over North East Creek U.S. 222 U.S. 40

  6. Contract No. - QA4605177MD 835C from East of Cockey Lane Relocated to MD 18ATown of StevensvilleResurfacing and Safety ImprovementsStorm Drains, Sidewalk, Geometric ImprovementsAdvertisement Date: November 5, 2013Notice to Proceed: February 17, 2014Approximate Hot Mix Asphalt Tonnage: 250 TonsApproximate Concrete Sidewalk Square Feet: 4,200 Square FeetApproximate Brick Sidewalk Square Feet: 1,600 Square Feet

  7. Contract No. - XY4055177Various Locations in Caroline CountyResurfacingAdvertisement Date: November 5, 2013Notice to Proceed: February 10, 2014Approximate Hot Mix Asphalt Tonnage: 35,000 TonsMD 314 from East of Cranby Street to MD 480; MD 313 from Structure #5027 to MD 314 Spur; MD16 from MD 331 to MD 578; Campground Road from One Block East of MD 404 to One Block West of MD 404 MD 16 MD 313

  8. Contract No. - XY4075177Various Locations in Cecil CountyResurfacingAdvertisement Date: November 5, 2013Notice to Proceed: February 17, 2014Approximate Hot Mix Asphalt Tonnage: 35,300 TonsU.S. 222 from MD 275 to Mill Street; MD 896 from the Delaware State Line to the Pennsylvania State Line; MD 274 from Post Road to Cecil Community College; MD 545 from MD 279 to Kirk Road; MD 285 from Lock Street to Lewis Street MD 274 U.S. 222

  9. Contract No. - AT3795177U.S. 50 from 0.5 Miles West of MD 404 to 0.5 Miles East of MD 404Resurfacing and Safety ImprovementsAdvertisement Date: December 3, 2013Notice to Proceed: Notice to Proceed Date: March 17, 2014Approximate Hot Mix Asphalt Tonnage: 6,000 TonsApproximate Concrete Pavement Square Yards: 700 Square Yards

  10. Contract No. - QA4845180Bridge #17030MD 313 Over Chester RiverBridge Deck ReplacementAdvertisement Date: December 10, 2013Notice to Proceed: March 24, 2014

  11. Contract No. - CE4465180MD 272 in Cecil CountyBridge #7036 over AmtrakProposed Bridge ReplacementAdvertise Date: January 7, 2014Notice to Proceed: April 21, 2014

  12. Contract No. – XY4205177Various Locations in Talbot CountyResurfacingAdvertisement Date: January 7, 2014Notice to Proceed: April 21, 2014Approximate Hot Mix Asphalt Tonnage: 32,750 TonsMD 33 from Seymour Avenue to Pea Neck Road; MD 33 from Easton Corporate Limits to Washington Street; MD 334 from MD 322 to End of S.H.A. Maintenance; MD 33 from Athletics Field to Marks Lane; MD 309 from U.S. 50 to Ball Park MD 334 MD 309

  13. Contract No. - QA4865177U.S. 50 from U.S. 301 to 0.5 Miles West of MD 404Resurfacing and Safety ImprovementsAdvertisement Date: February 14, 2014Notice to Proceed: May 19, 2014Approximate Hot Mix Asphalt Tonnage: 36,000 Tons

  14. Contract No. - TA3925171MD 331 over Choptank RiverBridge #20034Bridge ReplacementAdvertisement Date: March 4, 2014Notice to Proceed: June 16, 2014

  15. Contract No. - KE2955177MD 213, MD 290, and MD 313A in Kent CountyResurfacing and Safety ImprovementsLevel 1 ADA improvements, signal reconstructionAdvertisement Date: April 8, 2014Notice to Proceed: July 21, 2014Approximate Hot Mix Asphalt Tonnage: 3,000 TonsApproximate Square Feet of Concrete Sidewalk: 2,400 Square Feet

  16. Contract Number – CE2895177US 1 in Cecil CountyFrom MD 273A to Pennsylvania State LineProposed Resurfacing and Safety ImprovementsAdvertise Date: April 22, 2014Notice to Proceed: August 8, 2014Approximate Hot Mix Asphalt tonnage: 14,000 Tons

  17. Contract Number – QA2655170U.S. 301 at MD 304Proposed Interchange ConstructionAdvertise Date: June 3, 2014Notice to Proceed: September 15, 2014