High Plains Express (HPX) Transmission Project. Renewable Energy Transmission Authority October 10, 2007. 1. HPX Vision. Jointly explore opportunities to
E N D
High Plains Express (HPX)Transmission Project Renewable Energy Transmission Authority October 10, 2007 1
HPX Vision Jointly explore opportunities to expand the electric transmission grid in Wyoming, Colorado, New Mexico and Arizona to reliably meet the growing electricity needs by increasing access to renewable and other diverse resources within regional energy resource zones. 2
High-Voltage Transmission from WY – CO – NM - AZ Provide Transmission Path to “Energy Resource Zones” Allow Access to Economic Resources Integrate with Other Projects: Tot 3 Expansion Eastern Plains Transmission Project (EPTP) Northern New Mexico Import (NNMI) SunZia TransWest HPX Project Summary 3
HPX Participants • Colorado Springs Utilities • Platte River Power Authority • Public Service Company of New Mexico • Salt River Project • Trans-Elect Development Company • Tri-State Generation & Transmission • Western Area Power Administration • Xcel Energy (Public Service Company of Colorado) • Wyoming Infrastructure Authority (6/29/07) • New Mexico Energy, Minerals and Natural Resources Department (Renewable Energy Transmission Authority – RETA) (7/10/07) 4
Tot 3 Expansion Project TransWest EPTP NNMI Albuquerque HIGH PLAINS EXPRESS SunZia WYOMING Regional Map Energy Resource Zones Dave Johnston LRS Pawnee/ Story COLORADO Limon Midway Comanche Lamar Holcomb NEW MEXICO ARIZONA Gladstone Phoenix Socorro Tucson 5
Provide LSE’s in CO, NM, and AZ economic access to additional, diverse resources to meet rapid load growth Provide resource developers increased transmission capability to reach markets Improved regional reliability Increased regional import/export capability Minimize environmental impacts by sharing common corridors Help states meet renewable energy standards Project Benefits 6
HPX Process • Open process • Periodic stakeholder meetings • Meeting Held March 23, 2007 • Next meeting tentative November 14, 2007 (Denver) • Stakeholder input • Documents and reports are posted at: • http://www.rmao.com/wtpp/HPX_Studies.html 7
Jan Feb Mar Nov Apr May Jun July Aug Sep Oct Dec 2007 Schedule (Original) MOU Execution Stakeholder Meeting Technical Studies Recommendations Phase 2 FOR MORE INFO: http://www.rmao.com/wtpp/HPX_Studies.html thomas.green@xcelenergy.com 9
Project Milestone Schedule 2007 Schedule (Revised)
Progress - Studies • Participation • Weekly Conference Calls • Benchmarking • Map • Alternatives • Criteria 11
Studies – Remaining Analyses • Load Flow Analysis • Transmission Alternatives: • Single 500, Two 500, other? • Interaction with other projects • WY/CO, EPTP, etc. • Cost Estimates • Preliminary Siting • Report 12
Phase 2 - Development • Ownership / Participation Negotiations • Economics analyses • Siting studies • Detailed planning studies • Legal/Regulatory Implications 13
Questions 16