Progress on sub-task 1. Double length CLIC PETS

Progress on sub-task 1. Double length CLIC PETS. A. Lara, E Rodríguez, L. Sánchez and F. Toral CIEMAT 03/05/2011. PETS fabrication: copper rods. First copper rod is already at CIEMAT. Dimensional control OK. Seven copper rods are being machining. Expected to finish on week 21

lilian
Download Presentation

Progress on sub-task 1. Double length CLIC PETS

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Progress on sub-task 1. Double length CLIC PETS A. Lara, E Rodríguez, L. Sánchez and F. Toral CIEMAT 03/05/2011

  2. PETS fabrication: copper rods First copper rod is already at CIEMAT. Dimensional control OK. Seven copper rods are being machining. Expected to finish on week 21 SiC firing: 1000ºC /10-5 mbar/ 2 h Dimensional control of the first copper rod First copper rod

  3. PETS fabrication: couplers and tank COUPLERS AND TANK DESIGN IS FINISHED • Couplers are being machined at DMP, expected to finish on week 22. Brazing details are agreed with the brazing company (Ecor). • Mini tank is ordered, expected to be finished on week 24.

  4. PETS testing: design of the RF measurements Before brazing (optional). After brazing. COUPLERS MEASURING S11 AND S12 • Three different rings: • Lo (70 mm) • Lo +60 º (4.169mm) • Lo+120º (8.337mm) After brazing Before brazing

  5. PETS testing: design of the RF measurements Before EBW. Rods only. Measurement of S11 and S12. Measurements of the phase shift with antenna held by a digital ruler (accuracy 0.01 mm) . EIGTH RODS WITH DAMPING MATERIAL • After EBW. Rods + couplers. • Measurement of S11 and S12. • Bead pull measurements (optional). Before EBW After EBW

  6. PETS: future steps • Activities for the next months: • Finishing the bars, couplers and tank machining. • Brazing of one set of couplers at Ecor. • RF measurements of the copper rods before assembly. • Assembly of the rods by EBW at CERN.