1 / 22

Ensham Mine The Last Five Years and The Next Five

Delve into the history, operations, and future plans of Ensham Coal Mine, showcasing its growth, milestones, and potential for expansion. Explore the transition from open-cut to underground mining, equipment statistics, and production projections.

lindabell
Download Presentation

Ensham Mine The Last Five Years and The Next Five

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Ensham MineThe Last Five Years and The Next Five To Australian Institute of Mine Surveyors 19 August 2005 Presented by Graham Morris Manager, Technical Services

  2. ENSHAM MINE ENSHAM COAL MINE LOCATION

  3. ENSHAM LEASES AND MINE LAYOUT

  4. History

  5. Ensham Project History 1 • 1983 - Queensland Government release by tender, an area of 900 square kilometres for exploration. • 1984 - Grant of ATP426 on February 22, 1984 to a Joint Venture of 15 companies. • 1984-86 - Exploration of ATP426 by a consortium of 7. • 1987-90 - Rationalisation of JV parties to a group of 5. • 1990 - Minister for Resource Industries grants EP505 to a JV of 3.

  6. Ensham Project History 2 • 1991 - Contract confirmed with KEPCO (10 Yr). 2 mining lease applications lodged. Exploration commenced in Yongala area. • 1992 - ML70049 was applied for in June. Court action with previous JV partners settled. • 1993 - ML70049 – Yongala was granted in January. - Dragline walked 54 km to Ensham Lease. - First coal railings in September and first shipment in October. Stage 1 to 0.9Mtpa • 1994 - First shipment to KEPCO was delivered on time. Stage 2 to 1.6Mtpa development commenced in May.

  7. Ensham Project History 3 • 1995 - Coal haulage commenced from Pit C in January. Dragline walked to Pit D in March. • 1996 - Stage 3 to 5.5Mtpa development started in June. • 1997 - EPDC 20 year contract signed. EPDC became 4th Venture Owner (10%). • 1998 - First train railed from Ensham Load Out in October. - Ensham offices and accommodation built - P&H 9020 Dragline 2 build completed in September. - Coal mining started from Pit B

  8. Ensham Project History 4 • 1999 - 10 millionth tonne exported. Production stabilised at 5.5 Mtpa. Dragline 3 arrived BE1260 • 2000 – Yongala Pit stopped • 2002 – Management and strategy change started for further expansion, better design and control • 2003 – Pit A started • 2004 – Yongala Pit restarted in semi soft coking market. Dragline 4 ordered Bucyrus 8750

  9. IDEMITSU BLIGH COAL LG INTERNATIONAL EPDC (AUSTRALIA) QUEENSLAND PTY LIMITED (AUSTRALIA) PTY LTD PTY LTD 37.5 % 47.5 % 5.0 % 10.0 % JOINT VENTURE PARTNERS ENSHAM ENSHAM COAL RESOURCES SALES COAL SALES & DEVELOPMENT OPERATIONS MARKETING Ensham Coal Project Organisational Structure

  10. Major Equipment Items

  11. Dragline Statistics P&H 9020-20E 97.5m 87.5m 48.0m 57.9m 2.3m 5,503 t 90m3 150t 66kv 21Mbm3 14 hrs 1998 2,230 MARION 8050-38 99m 86.3m 45.7m 54.9m 1.9m 2,862 t 47m3 80t 66kv 13Mbm3 12 hrs 1981 1,875 BE 1260 87m 75m 44m 35m 2.2m 1,676 t 26m3 44t 66kv 8Mbm3 4hrs Mid 1970’s Boom Length (Centreline) Operating Radius Dump Height Dig Depth (Geometric) Length of Step Working Weight Nominal Bucket Capacity Nominal Bucket Capacity Power Input Quantity Moved Per Year Time to Walk 1 km Year of commissioning Peak Horse Power

  12. Mobile Equipment • Drill & Blast – Brandrill, Coldwell, Orica • Pre Strip – Goldings, HSE • Earthworks – Grahams Plant Hire, Edgewoods • Coal Mining - Ensham

  13. Excavation Fleet

  14. Production

  15. Project Production Profile

  16. Sales Mix for CY2003 & CY2004

  17. Projects

  18. Open Cut Continuing Expansion • Introduction of Dragline 4 - BE8750 January 2007 • Move draglines to new locations • Lowering cost profile • Production capability to 13Mt/y

  19. Underground Project • Several opportunities – North, Central, South • Central & South Mine mineable resource 724Mt >2.5m • Longwall mine target capacity ~7Mt/y • Longwall Target date 2010

  20. Ensham’s Future – Proposed Underground Mine Layouts

  21. Underground Project Status • Exploration Phase for Central Area • 2D seismic survey completed 2005 • Drilling in progress • 3D seismic survey to occur 2005 • Entry options being considered

  22. Production Future Profile

More Related