110 likes | 292 Views
North Cumbria – recent rollout and progress. ForWard. Introductions. Laura Parkinson – Project Manager Joan Markwell – Benefits & Change Manager David Young – PAS Manager. ForWard Programme. IM&T Strategy Clinically led transformation, enabled by technology Four steps: RealTime
E N D
Introductions • Laura Parkinson – Project Manager • Joan Markwell – Benefits & Change Manager • David Young – PAS Manager
ForWard Programme • IM&T Strategy • Clinically led transformation, enabled by technology • Four steps: • RealTime • Electronic Observations • Order Comms • ePrescribing • Underpinned by SSO & Wireless LAN
A Brief History • Placed order September 2010 • Software installed October 2010 • Organisation in turnaround • Nursing Review • Senior Management turnover • Acquisition! • ForWard adopted by QIPP • Green light to roll-out – 16th June 2011 • Patterdale (EMAU) & Pillar (general medical) – 5th Oct • Honister 1 & 2 - 5th Dec
From Day One • Bed Management – bi-directional PAS link (iSoft iExPRess) • Discharge Planning (conditions, TLOS) • Produce electronic discharge summaries for GPs (print & fax) • Refer patients to Social Services or STINT (Contact 1) (print & fax) • Record nursing paperwork • Record VTE assessments • Electronic handover between shifts • Referral to Hospital at Night teams out of hours • Monitor infection outbreaks – link to Pathology system (iSoft Tpath)
Forms • Currently • Inpatient Assessment • Bed Safety Rails • DIAG • Derby Nutritional Score • Falls Care Plan • Waterlow Plan • Discharge Summary • VTE • Contact 1 (DTOC) • Nurse-led discharge • Planned • ?Liverpool Care Pathway
Roll-out approach • Two/three wards at a time, every five weeks • Business change engagement • Adapt generic process • Identify any new requirements • End-user training delivered over three weeks • Two weeks floorwalking support • On-site 07:00 – 22:00, on-call overnight • ForWard Coordinator • Next!
Challenges • Limited organisational buy-in • Huge change to working processes for all staff • Small team = long roll-out, but still challenging • Releasing staff for training • SSO/Smartcards • Interfaces • Doctors • Discharge Summaries, VTEs
Benefits • Up-to-date, accurate information on patients • ADTs, consultant, conditions, assessments • Patient information more widely available, yet more secure • Nursing assessments • Better quality input (mandatory fields) • Lack of duplication • Improved communication between staff (at handover) • Improved bed management/planning
Future Plans • Continue roll-out • Support wards already live/enhance use of RT • More forms • Develop care pathways • Electronic Observations – development partnership • Other ForWard Programme projects: • SSO & Context Management in A&E • Order Comms • ePrescribing
Thank You! Any Questions?