100 likes | 308 Views
State Estimator (SE) and Simultaneous Feasibility Test (SFT) Status Report. Steve Myers Manager of System Operations. State Estimator. Progress Total difference between generation & load reduced from 10’s of 1000’s at first to <500 MW Approximately 25 buses >50 MW mismatch
E N D
State Estimator (SE)andSimultaneous Feasibility Test (SFT)Status Report Steve Myers Manager of System Operations
State Estimator • Progress • Total difference between generation & load reduced from 10’s of 1000’s at first to <500 MW • Approximately 25 buses >50 MW mismatch • 90% observability (75% with measurements)
Uses of the State Estimator • Identifying data problems • Identifying model problems • Monitoring of locations w/o SCADA (by System Operators) • Creating a case for Contingency Analysis • Normally successful at least once per day
SE Plan • Continue to incrementally improve • Continue to reduce mismatches • With Engineer’s attention, use in Day-Ahead analysis • Train System Operators • Ultimately – SE will run CA in RT sequence
SE Plan • Needs • Data Response from QSE’s and Private Networks • Unit Status – QSE • Private Network Issues to Correct • Net Gen sent as one unit • Loads not modeled • Data required by ERCOT Operating Guides Section 8
Simultaneous Feasibility Test (SFT) • Calculates “Shift Factors” used in Congestion Management • Progress • Attempted use in December '02 • Bugs that had not shown up in test mode • Waiting on fixes from vendor • Once offline testing complete, will test again in production
SFT Plan • Use in Day-Ahead • Initially peak hour • Limited contingencies • Use in Hours Ahead • Initially test mode • Limited contingencies • Limited iterations with SPD
Next Steps • Contingency Analysis will run in the Real-Time sequence and upon demand • SE and SFT will run for each BES deployment • ERCOT expects its systems to be ready By April 1
What Do We Gain? • More accurate analyses – closer to RT • Greatly improved pro-active CM • Much more accurate “Shift Factors” • Potentially less OOM deployments