LCLS Photon Systems Installation and Commissioning. Hal Tompkins LCLS Photon Systems Deputy Manager. Presentation to Facility Advisory Committee October 29, 2007. Important Dates. Beam Dump Co-occupancy - 12/5/07 FEE and NEH Co-occupancy - 12/21/07
E N D
LCLS Photon Systems Installation and Commissioning Hal Tompkins LCLS Photon Systems Deputy Manager Presentation to Facility Advisory Committee October 29, 2007
Important Dates • Beam Dump Co-occupancy - 12/5/07 • FEE and NEH Co-occupancy - 12/21/07 • FEE and NEH Beneficial Occupancy - 3/21/08 (NEH elevator - 4/08?) • X-Ray Transport Tunnel Co-occupancy - 1/08/08 • FEH Co-occupancy - 3/24/08 • Tunnel/FEH Beneficial Occupancy - 6/23/08
Beam Dump Installation • Electron beam dump installations are critical. • Must install two electron-photon stopper systems, fast shutter, collimator, penetration tube, and backfill steel and concrete in Muon Wall 1. • Expect to certify PPS though electron beam dump in 10/09. • This allows electrons into BTH, UH, etc.
FEE Installation • Fixed Mask, Adjustable Slits, Gas Detectors, and Gas Attenuator make up phase 1 (June 11-July 1, 2008). • Calorimeter, K-spectrometer, Soft X-ray imager, and Direct imager make up phase 2 (July 2-23, 2008). • Soft x-ray Offset Mirror System (SOMS) is phase 3 (Jan. 16-Feb. 5, 2009). • Note the gap between phase 2 and phase 3. This is driven by deferring purchase of the FEE Mech/Vac (mainly collimators) and pop-in monitors to FY09 for budgetary reasons. It is not driven by delivery date of SOMS mirror substrates. • Hard x-ray Offset Mirror System (HOMS) is phase 4. This is close to being delivery-date dependent (Feb. 6-26, 2009). • PPS/BCS installed by 2/09.
NEH Installation • Vacuum transport through hutches 1 and 2 will be installed. • Anticipate LUSI will handle vacuum transport in hutch 3. • XES laser installation begins with NEH B.O. and is expected to be complete in 5/09. Commissioning the laser diagnostics and controls follows immediately afterwards. • AMO experiment installation begins with NEH B.O. and is slated to be complete in 7/09.
Tunnel/FEH Installation • X-Ray Tunnel and Far Experimental Hall component purchases also delayed until FY09. • FEH hutch construction estimated at 8-9 months.
Commissioning • Nominal first beam to FEE is 5/14/09 • Commission the X-ray diagnostics simultaneously with commissioning the undulator. • Start with Direct Imager, then move on to Adjustable Slits, Gas Detectors, the Attenuators, and the Calorimeter. • Then do K-spectrometer and Soft X-ray Imager. • Align and characterize the spontaneous radiation beam • Measure photon flux per pulse • Find SASE and optimize gain (first at low energy) • Deliver beam through offset mirror systems to experiments in NEH hutches.
Commissioning • Stabilize FEL for User Run • User Run • SLAC shutdown • Recommission upstream pieces of LCLS • If ready, transport x-rays into Tunnel and Far Hall • Detect x-rays in Far Hall - complete CD 4 • Continue working on lasing at higher energies • Alternate machine work with experiments
Summary • Very tight schedule between first beam to FEE and User Run - driven by FY08 budget limitations. • Very tight schedule between AMO experiment installation and User Run - driven by FY08 budget limitations. • We think we have a good shot at lasing at 1.5 nm for the User Run - stability is a bigger question. • Operation at .15 nm for the User Run will likely be with spontaneous radiation.
Detailed FEE Vacuum Installation Schedule • Install vacuum system 65d Thu 3/27/08 Wed 6/25/08 • install fixed mask/valve 3d Thu 3/27/08 Mon 3/31/08 • align fixed mask/valve 2d Tue 4/1/08 Wed 4/2/08 • install slit system 4d Tue 4/1/08 Fri 4/4/08 • align slit system 2d Mon 4/7/08 Tue 4/8/08 • install attenuators/gas detectors 8d Mon 4/7/08 Wed 4/16/08 • install K-spectrometer 2d Thu 4/17/08 Fri 4/18/08 • align attenuators/gas detectors 4d Thu 4/17/08 Tue 4/22/08 • install calorimeter 3d Mon 4/21/08 Wed 4/23/08 • align K-spectrometer 1d Wed 4/23/08 Wed 4/23/08 • align calorimeter 1d Thu 4/24/08 Thu 4/24/08 • install direct imager 2d Thu 4/24/08 Fri 4/25/08 • install isolation valve 0.5d Mon 4/28/08 Mon 4/28/08 • align direct imager 1d Mon 4/28/08 Mon 4/28/08 • install differential pumping section 1d Mon 4/28/08 Tue 4/29/08 • install collimator C1 0.5d Tue 4/29/08 Tue 4/29/08 • align diff. pump. section 1d Tue 4/29/08 Wed 4/30/08 • install SOMS M1S 2d Wed 4/30/08 Thu 5/1/08 • align collimator C1 0.5d Wed 4/30/08 Wed 4/30/08
Detailed FEE Vacuum Installation Schedule (cont.) • align SOMS M1S 1d Fri 5/2/08 Fri 5/2/08 • install HOMS M1H 2d Fri 5/2/08 Mon 5/5/08 • install SOMS M2S 2d Fri 5/2/08 Mon 5/5/08 • align HOMS M1H 1d Tue 5/6/08 Tue 5/6/08 • install collimators C2S 1d Tue 5/6/08 Tue 5/6/08 • align collimators C2S 0.5d Wed 5/7/08 Wed 5/7/08 • install HOMS C2H 0.5d Wed 5/7/08 Wed 5/7/08 • align SOMS M2S 1d Wed 5/7/08 Wed 5/7/08 • install HOMS M2H 2d Wed 5/7/08 Fri 5/9/08 • align HOMS C2H & M2H 1d Fri 5/9/08 Mon 5/12/08 • install FEE/NEH beam pipes (3) 2d Fri 5/9/08 Tue 5/13/08 • align FEE/NEH beam pipes (3) 1d Tue 5/13/08 Wed 5/14/08 • backfill wall 1 window 10d Wed 5/14/08 Wed 5/28/08 • install C3H, C3S1, & C3S2 collimators 2d Wed 5/28/08 Fri 5/30/08 • align C3H, C3S1, & C3S2 collimators 1d Fri 5/30/08 Mon 6/2/08
Detailed FEE Vacuum Installation Schedule (cont.) • fix collimator positions per RP 2d Mon 6/2/08 Wed 6/4/08 • install HXR stoppers 3d Mon 6/2/08 Thu 6/5/08 • Install SXR stoppers 3d Thu 6/5/08 Tue 6/10/08 • install HXR diff. pump. Section 0.5d Tue 6/10/08 Tue 6/10/08 • align HXR & SXR stoppers 1d Tue 6/10/08 Wed 6/11/08 • install SOMS M3S & M4S 3d Wed 6/11/08 Fri 6/13/08 • install isolation valves 3d Mon 6/16/08 Wed 6/18/08 • align isolation valves 1d Thu 6/19/08 Thu 6/19/08 • install vacuum piping 2d Thu 6/19/08 Fri 6/20/08 • install shadow wall 3d Mon 6/23/08 Wed 6/25/08 • install ion pumps 3d Mon 6/23/08 Wed 6/25/08