An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. LCLS Photon Systems Installation and Commissioning Hal Tompkins LCLS Photon Systems Deputy Manager Presentation to Facility Advisory Committee October 29, 2007

  2. Important Dates • Beam Dump Co-occupancy - 12/5/07 • FEE and NEH Co-occupancy - 12/21/07 • FEE and NEH Beneficial Occupancy - 3/21/08 (NEH elevator - 4/08?) • X-Ray Transport Tunnel Co-occupancy - 1/08/08 • FEH Co-occupancy - 3/24/08 • Tunnel/FEH Beneficial Occupancy - 6/23/08

  3. FEE Layout

  4. NEH Layout

  5. Beam Dump Installation • Electron beam dump installations are critical. • Must install two electron-photon stopper systems, fast shutter, collimator, penetration tube, and backfill steel and concrete in Muon Wall 1. • Expect to certify PPS though electron beam dump in 10/09. • This allows electrons into BTH, UH, etc.

  6. FEE Installation • Fixed Mask, Adjustable Slits, Gas Detectors, and Gas Attenuator make up phase 1 (June 11-July 1, 2008). • Calorimeter, K-spectrometer, Soft X-ray imager, and Direct imager make up phase 2 (July 2-23, 2008). • Soft x-ray Offset Mirror System (SOMS) is phase 3 (Jan. 16-Feb. 5, 2009). • Note the gap between phase 2 and phase 3. This is driven by deferring purchase of the FEE Mech/Vac (mainly collimators) and pop-in monitors to FY09 for budgetary reasons. It is not driven by delivery date of SOMS mirror substrates. • Hard x-ray Offset Mirror System (HOMS) is phase 4. This is close to being delivery-date dependent (Feb. 6-26, 2009). • PPS/BCS installed by 2/09.

  7. NEH Installation • Vacuum transport through hutches 1 and 2 will be installed. • Anticipate LUSI will handle vacuum transport in hutch 3. • XES laser installation begins with NEH B.O. and is expected to be complete in 5/09. Commissioning the laser diagnostics and controls follows immediately afterwards. • AMO experiment installation begins with NEH B.O. and is slated to be complete in 7/09.

  8. Tunnel/FEH Installation • X-Ray Tunnel and Far Experimental Hall component purchases also delayed until FY09. • FEH hutch construction estimated at 8-9 months.

  9. FEL Commissioning Timeline

  10. Commissioning • Nominal first beam to FEE is 5/14/09 • Commission the X-ray diagnostics simultaneously with commissioning the undulator. • Start with Direct Imager, then move on to Adjustable Slits, Gas Detectors, the Attenuators, and the Calorimeter. • Then do K-spectrometer and Soft X-ray Imager. • Align and characterize the spontaneous radiation beam • Measure photon flux per pulse • Find SASE and optimize gain (first at low energy) • Deliver beam through offset mirror systems to experiments in NEH hutches.

  11. Commissioning • Stabilize FEL for User Run • User Run • SLAC shutdown • Recommission upstream pieces of LCLS • If ready, transport x-rays into Tunnel and Far Hall • Detect x-rays in Far Hall - complete CD 4 • Continue working on lasing at higher energies • Alternate machine work with experiments

  12. Summary • Very tight schedule between first beam to FEE and User Run - driven by FY08 budget limitations. • Very tight schedule between AMO experiment installation and User Run - driven by FY08 budget limitations. • We think we have a good shot at lasing at 1.5 nm for the User Run - stability is a bigger question. • Operation at .15 nm for the User Run will likely be with spontaneous radiation.

  13. End of Presentation

  14. Detailed FEE Vacuum Installation Schedule • Install vacuum system 65d Thu 3/27/08 Wed 6/25/08 • install fixed mask/valve 3d Thu 3/27/08 Mon 3/31/08 • align fixed mask/valve 2d Tue 4/1/08 Wed 4/2/08 • install slit system 4d Tue 4/1/08 Fri 4/4/08 • align slit system 2d Mon 4/7/08 Tue 4/8/08 • install attenuators/gas detectors 8d Mon 4/7/08 Wed 4/16/08 • install K-spectrometer 2d Thu 4/17/08 Fri 4/18/08 • align attenuators/gas detectors 4d Thu 4/17/08 Tue 4/22/08 • install calorimeter 3d Mon 4/21/08 Wed 4/23/08 • align K-spectrometer 1d Wed 4/23/08 Wed 4/23/08 • align calorimeter 1d Thu 4/24/08 Thu 4/24/08 • install direct imager 2d Thu 4/24/08 Fri 4/25/08 • install isolation valve 0.5d Mon 4/28/08 Mon 4/28/08 • align direct imager 1d Mon 4/28/08 Mon 4/28/08 • install differential pumping section 1d Mon 4/28/08 Tue 4/29/08 • install collimator C1 0.5d Tue 4/29/08 Tue 4/29/08 • align diff. pump. section 1d Tue 4/29/08 Wed 4/30/08 • install SOMS M1S 2d Wed 4/30/08 Thu 5/1/08 • align collimator C1 0.5d Wed 4/30/08 Wed 4/30/08

  15. Detailed FEE Vacuum Installation Schedule (cont.) • align SOMS M1S 1d Fri 5/2/08 Fri 5/2/08 • install HOMS M1H 2d Fri 5/2/08 Mon 5/5/08 • install SOMS M2S 2d Fri 5/2/08 Mon 5/5/08 • align HOMS M1H 1d Tue 5/6/08 Tue 5/6/08 • install collimators C2S 1d Tue 5/6/08 Tue 5/6/08 • align collimators C2S 0.5d Wed 5/7/08 Wed 5/7/08 • install HOMS C2H 0.5d Wed 5/7/08 Wed 5/7/08 • align SOMS M2S 1d Wed 5/7/08 Wed 5/7/08 • install HOMS M2H 2d Wed 5/7/08 Fri 5/9/08 • align HOMS C2H & M2H 1d Fri 5/9/08 Mon 5/12/08 • install FEE/NEH beam pipes (3) 2d Fri 5/9/08 Tue 5/13/08 • align FEE/NEH beam pipes (3) 1d Tue 5/13/08 Wed 5/14/08 • backfill wall 1 window 10d Wed 5/14/08 Wed 5/28/08 • install C3H, C3S1, & C3S2 collimators 2d Wed 5/28/08 Fri 5/30/08 • align C3H, C3S1, & C3S2 collimators 1d Fri 5/30/08 Mon 6/2/08

  16. Detailed FEE Vacuum Installation Schedule (cont.) • fix collimator positions per RP 2d Mon 6/2/08 Wed 6/4/08 • install HXR stoppers 3d Mon 6/2/08 Thu 6/5/08 • Install SXR stoppers 3d Thu 6/5/08 Tue 6/10/08 • install HXR diff. pump. Section 0.5d Tue 6/10/08 Tue 6/10/08 • align HXR & SXR stoppers 1d Tue 6/10/08 Wed 6/11/08 • install SOMS M3S & M4S 3d Wed 6/11/08 Fri 6/13/08 • install isolation valves 3d Mon 6/16/08 Wed 6/18/08 • align isolation valves 1d Thu 6/19/08 Thu 6/19/08 • install vacuum piping 2d Thu 6/19/08 Fri 6/20/08 • install shadow wall 3d Mon 6/23/08 Wed 6/25/08 • install ion pumps 3d Mon 6/23/08 Wed 6/25/08

  17. Commissioning Schedule

  18. Commissioning Schedule (cont.)

  19. Commissioning Schedule (cont.)

  20. Commissioning Schedule (cont.)