Production Plans

This document outlines the production plans for the Muon DT Minicrate System at CERN. It includes installation plans and details on the production of the Minicrates.

lminard
Download Presentation

Production Plans

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Production Plans ESR for the muon DT Minicrate System CERN. November 3rd 2003.

  2. CHAMBER AND MC INSTALLATION PLANS 4 3 5 2 6 05 YB+2 1 7 12 8 11 9 10 4 4 4 4 3 3 3 3 5 5 5 5 4 4 4 4 3 3 2 2 2 2 3 3 5 5 5 5 4 4 4 4 4 3 3 3 3 3 5 5 5 5 5 6 6 6 6 2 2 2 2 4 4 4 4 4 4 4 4 3 3 2 2 2 2 3 2 3 3 3 3 3 5 5 5 5 5 5 6 6 5 5 6 6 6 6 6 6 6 2 2 2 2 2 2 2 2 6 6 6 6 6 6 6 6 YB-1 YB-1 YB0 YB-2 1 1 1 1 7 7 7 7 YB-1 YB-1 YB-1 YB-1 1 1 1 1 YB+2 YB+2 YB+1 YB+1 YB0 7 7 7 7 1 1 1 1 1 7 7 7 7 7 YB+1 YB+1 YB0 YB+1 YB+1 YB0 YB0 YB0 1 1 1 1 1 1 1 1 7 7 7 7 7 7 7 7 12 12 12 12 8 8 8 8 12 12 12 12 11 11 11 11 12 12 12 12 12 8 8 8 8 9 9 9 9 8 8 8 8 8 10 10 10 10 11 11 11 11 12 12 12 12 12 12 12 12 11 11 11 11 11 9 9 9 9 8 8 8 8 8 8 8 8 10 10 9 9 9 9 10 10 9 10 10 10 10 10 11 11 11 11 11 11 11 11 9 9 9 9 9 9 9 9 10 10 10 10 10 10 10 10 4 4 4 4 4 3 3 3 3 3 5 5 5 5 5 4 4 4 2 2 2 2 2 3 3 3 5 5 5 6 6 6 6 6 2 2 2 6 6 6 YB-2 YB-2 YB-2 YB-2 YB-2 1 1 1 1 1 YB-1,-2 rest 7 7 7 7 7 YB+2 YB+2 YB+2 1 1 1 7 7 7 12 12 12 12 12 8 8 8 8 8 12 12 12 11 11 11 11 11 8 8 8 9 9 9 9 9 10 10 10 10 10 11 11 11 9 9 9 10 10 10 Chambers installed with MC Chambers installed without MC YB+1,+2 sectors 8 to 12 (MB1): 10 ch YB0, YB+1, YB+2 sectors 9 to 11 (MB4): 12 ch YB-1 sectors 8 & 9 (MB1): 2 ch YB+1, YB+2 sectors 8 to 12 (MB2,3): 20 ch YB-1 sectors 8 & 9 (MB2 & MB3): 4 ch YB-2 sectors 8 to 9 (MB1,2 & 3): 6 ch YB0 sectors 8 to 12 (MB1,2 & 3): 15 ch YB+1,+2 sectors 2 to 6 (all): 42 ch YB-1,-2 sectors 8 & 9 (MB4): 4 ch YB0 sectors 2 to 6 (all): 21 ch

  3. MC PRODUCTION PLANS 3 ESR / MUON DT MINICRATE SYSTEM. Production Plans. November 3rd , 2003 21 Minicrates must be ready before May 2004 Magnet test Ch installed without MC @ 12 MC per month

  4. 4 ESR / MUON DT MINICRATE SYSTEM. Production Plans. November 3rd , 2003 FIRST 21 MC´s PRODUCTION PLANNING

  5. 5 MC ASSEMBLY PLANS ASEMBLY PLAN: CIEMAT (Madrid): - Will receive the MC mechanical pieces and assemble them. - Assemble the Read-Out part and its cabling. - Assemble the CCB, SB and CCB link (needed for testing) and its cabling. - Test proper operation of Read-Out and CCB+link. Shift - Install the TRB´s and  signal and rest of cables and close the MC. - Test proper operation of Read-Out and Trigger. INFN (Padova/Legnaro): Shift - Install MC on chambers. - Test whole MC with chambers. ISR (CERN): SX5 (CERN): - Installation on wheels. ESR / MUON DT MINICRATE SYSTEM. Production Plans. November 3rd , 2003

  6. 6 MC PRODUCTION PLANS Madrid Padova Torino Aachen MC boxes (MB4) MC boxes (MB1) MC boxes (MB3) CCB MC boxes (MB2) I2C pigtail cables Bologna PS Filters Mechanical pieces SB boards CCB link ROB FE cables RO link TRB Cabling ESR / MUON DT MINICRATE SYSTEM. Production Plans. November 3rd , 2003 LIST OF MATERIAL

  7. 7 ESR / MUON DT MINICRATE SYSTEM. Production Plans. November 3rd , 2003 CONCLUSIONS Every item of a Minicrate have already been prototyped, tested and modified to meet their requirements. Diverse and exhaustive tests have being performed to insure proper operation. All items are ready for launching final production. Existing software for each part is being integrated in a full operation system that will be used for testing complete MC in Madrid, Padova and CERN. In order to be on time with chamber installation planning, MC production should start as soon as possible.