1 / 19

PARCA: Contractual Overview

PARCA: Contractual Overview. TX Workgroup 27 th February 2013. Steve Pownall. Purpose of today…. Is to provide an overview of PARCA contract as follows: Pre-PARCA Assessment (proforma) PARCA Phased ‘Works’ Provision of capacity inc ‘fine tuning’ Customer fees and financial commitment

loan
Download Presentation

PARCA: Contractual Overview

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. PARCA: Contractual Overview TX Workgroup 27th February 2013 Steve Pownall

  2. Purpose of today… Is to provide an overview of PARCA contract as follows: • Pre-PARCA Assessment (proforma) • PARCA Phased ‘Works’ • Provision of capacity inc ‘fine tuning’ • Customer fees and financial commitment • Information provision • Demonstration Data • Milestone Information

  3. …but before we commence.. • Going forward, for the purposes of the proposed ‘PARCA’ contract /arrangements ONLY, we intend to use a simplified naming convention: WasWill becomeWorks Stage 1a Phase 1 Needs Case/Technical Options Stage 1b Phase 2, Schedule A Strategic Options Stage 2 Phase 2, Schedule B Outline routing & siting Stage 3 Phase 2, Schedule C Detailed routing & siting / EIA Stage 4 Phase 2, Schedule D Proposed DCO Application Stage 5 Phase 2, Schedule E Submit DCO Application / hearings Stage 6 Phase 2, Schedule F Secretary of State decision Note: ‘Local Planning’ Works will be under Phase 2, Schedule G (to be defined)

  4. Pre-PARCA Assessment • Customer to provide the following information to National Grid: • Details of customer • Proposed project location including facility site and NTS connection site • Indicative capacity requirement (profiled if appropriate) • Indicative capacity upper/lower range – for ‘fine tuning’ purposes only • For DNO Users; Pressure and Flex requirements • Used to populate the PARCA data items prior to signature by both parties • We anticipate dialogue between the customer and National Grid prior to the submission of this information

  5. PARCA Phased Works - Overview (1) The PARCA Works will be contained within two Phases • Phase 1 - Needs Case & Technical Options • Where no NTS reinforcement is required the PARCA becomes primarily a customer ‘Demonstration Data’ contract up to point of capacity allocation • Phase 2 - Statutory Planning Works either: • National planning (Planning Act 2008) for Development Consent Order • Schedules A - F (please see below) • Or: • Local planning • Schedule G [to be defined] • Note: Where we identify NTS reinforcement that requires planning, this could be met through either build or through non-build alternatives e.g. commercial contract or a combination of both. We anticipate that a proportion of the Phase 2 Statutory Planning Works will still need to be carried out under an alternative to a full-build option.

  6. PARCA Phased Works - Overview (2) • Two natural ‘customer’ breakpoints • Following output from Phase 1 • Customer to indicate whether it wishes to progress to Phase 2 - if NG indicates a Needs Case for NTS reinforcement • Where no NTS reinforcement is identified the customer will be required to pay a reservation fee; or the customer may bid through the capacity auction process • Phase 2 - following Secretary of State (or local authority) decision on our planning application • Customer may terminate PARCA Works at any time but liable for costs incurred (and committed) up to the point of termination

  7. PARCA Phase 1 Works: Establish Needs Case and Technical Options

  8. PARCA Phase 2 Works: Schedule A – Strategic Options works

  9. PARCA Phase 2 Works: Schedule B – Outline Routing and Siting works

  10. PARCA Phase 2 Works: Schedule C – Detailed Routing & Siting works

  11. PARCA Phase 2 Works:Schedules D, E and F Milestone Information: Provide customer with update ‘report’, reconfirm NG Project Plan timescales, as necessary for each schedule

  12. Provision of Capacity timeline (1) • Effective Date (ED): • At which the customer and National Grid sign the PARCA • From which National Grid agrees to undertake Phase 1 Works – will require the customer to pay the fee prior to commencement of the Works • Reservation Date (RsD): • The customer will have its capacity requirement reserved • Allocation Date (AD): • The customer (where not a User) must have nominated one (or more) User(s) up to 1 month prior to this date • The default date that is between 24 and 35 months prior to the Registration Date • Registration Date (RgD): • Date from which the User holds the capacity

  13. Reservation Date (RsD) Allocation Date (AD) Registration Date (RgD) RsD AD RgD Nominate user up to 1 month before AD PARCA: Phase 1 Works Date from which the User holds the capacity Date PARCA signed by the customer and National Grid • Price • NPV (entry only) • Quantity (& range) reservation fee or security due • Capacity ‘tagged’ in Gemini from this date and no longer forms part of unsold. • Capacity allocated to the User • NPV (entry only) Default Allocation Date is between 24 and 35 months prior to the RgD Provision of Capacity timeline (2) Effective Date (ED) ED

  14. Provision of Capacity & ‘fine tuning’ Fine tuning of customer’s capacity requirement: • Customers have requested the flexibility to ‘fine tune’ their capacity requirement prior to the capacity Allocation Date • As a project progresses, a customer will have more certainty as to its ‘final’ capacity requirement: linked to a number of factors e.g. chosen turbine manufacturer • We understand that capacity fine-tuning is an important customer consideration • Fine tuning will be allowed within an agreed upper and lower range • Pre-PARCA Assessment proforma • We will require the customer to provide demonstration data to support its request to fine tune its capacity requirement

  15. Customer fees and financial commitment (1) PARCA Phase 1 (Needs Case and Technical Options) Fee • Customer will fully fund the PARCA Phase 1 Works: fee approx £120,000 ~ £150,000 – similar principles to 0373 NTS Connection (excluded service, cost pass through) • Fee reconciled against outturn costs with ££ difference refunded to, or recovered from, the customer PARCA Phase 2 (Statutory Planning Works) - securitisation • Where Phase 1 Works identifies either: • Requirement for physical NTS reinforcement and, Local or National planning consent is required or; • Use of a commercial contract can be utilised to meet the customer’s capacity requirement then: • The customer will securitise 100% of the proposed Pre-Capacity Allocation Revenue Driver(see last TX Workgroup PARCA Funding presentation for details)

  16. Customer fees and financial commitment (2) Capacity Reservation Fee • This could be applied following the completion of PARCA Phase 1 Works, where the customer’s capacity requirement will be met entirely through existing system capability • In this scenario, the customer may secure its capacity requirement either by bidding in the capacity auction or by reserving through the PARCA • The Capacity Reservation Fee could be calculated: • Following PARCA Phase 1 Works and customer agreeing that it wishes to progress its project • The Capacity Reservation Fee will be calculated based on (to be discussed in March TX Workgroup)

  17. PARCA Funding (revised for ‘Phases’) Proposal for a Planning Act 2008 project Phase 1 Works Phase 2 Works NTS Investment: Project Needs Case / Technical Options NTS Reinforcement (or other commercial method) required PARCA Phase Strategic Options Schedule A Outline Routing & siting Schedule B Detailed EIA Routing & siting Schedule C Proposed DCO Application Schedule D DCO Application and hearings Schedule E DCO submission & SoS decision Schedule F X Pre-Capacity Allocation Revenue Driver calculated by end of Phase 1 Pre-Capacity Allocation Revenue Driver triggered and profiled over 4 years X Post-Capacity Allocation RD triggered & profiled over 3 yrs Post-Capacity Allocation Revenue Driver calc’d during Phase 2 Appendix 3 X X All costs charged to PARCA Signatory Classified as 100% Excluded Services – no impact on Allowed Revenue Invoiced up front and reconciled Post Capacity Allocation RD triggered RD* added to Allowed Revenue and charged to industry via Transportation Charges Pre Capacity Allocation Revenue Driver triggered RD* added to Allowed Revenue and charged to industry via Transportation Charges. PARCA Signatory securitises value of RD Pre Capacity Revenue Driver runs up to DCO Funding / Charging 17 *Value of RD’s are reconciled with actual costs, reconciliations through Transportation charges.

  18. Information Provision Demonstration Data (from customer) • Please see overview… • Most categories seem to be required towards the end of the PARCA process e.g. Phase 2, Schedules E, F • We would appreciate views (please!) from all categories of our customers e.g. entry, storage and exit as to whether there might be additional items PARCA Phased Works – Milestone Information (from National Grid) • Please see overview… • The proposed categories of information that customers will receive from National Grid are aligned to the PARCA Phased Works and associated milestones • Is there any other additional information that customers might wish to see from National Grid?

  19. And finally… Do you have any further questions, comments?

More Related