DoI Industry Forum Remote Housing Construction Program 2013 -2018. Joint Presenters; Don Dowling, Executive Director, Department of Infrastructure Phillip Luck, Program Director, Department of Housing. 30 May 2013. Housing Programs.
E N D
DoI Industry ForumRemote Housing Construction Program2013 -2018 Joint Presenters; Don Dowling, Executive Director, Department of Infrastructure Phillip Luck, Program Director, Department of Housing 30 May 2013
Housing Programs National Partnership Agreement – Remote Indigenous Housing (NPARIH) Stronger Futures NT Government Employee Housing Public Housing
Program Targets ($2.0 B – 2008/18) NPARIH $1.7 Billion SFNT $260 Million
Key NPARIH/SFNT Objectives Significantly reduce overcrowding Increasing the supply of new houses and improving the condition of existing houses in remote Indigenous communities Ensuring that rental houses are well maintained and managed in remote Indigenous Communities Create opportunity for Indigenous Economic Development (all NPAs have this requirement) Deliver targets within budget, cost parameters and timelines.
Delivery Strategy Alliances DoI – Panel Contractors (+) Indigenous Business Enterprises, Shires and local community based contractors
DoI Delivery Model 3 Panels for Upgrades and New House construction (Below $5m and Above $5m), in each of the 5 regions. Generally works are packaged based on a single community or a group of communities. Upgrades are both minor and major to achieve a Remote Housing Standard. New Housing is of standard designs that meet the NPARIH Design Guidelines and Performance Specifications. New houses are to be replacement houses or constructed on existing serviced lots
Timeline SIHIP ends June 2013 Stronger Futures 2012 -2018 3500 Upgrades over 73 locations NPARIH Post June 2013 – June 2018 522 Replacement houses Housing related infrastructure upgrades
Conditions of Tendering Local development Indigenous development plan (20%) Industry participation plan Quality management plan Alternative tenders allowed Modify existing design Propose new design Propose different house mix (All subject to DHsg approval)
Indigenous Development Plan Mandatory 20% indigenous employment Community Contacts JSAs - Jobfind / ITEC Shires Councils\ FaHCSIA – GEC Community Employee / Training Programs Community Services Local business Stores Contractors Obligations PPE White cards and other mandatory training Reporting
Quality Management Plan NTG and AG Audits Nominate Quality Manager Submit quality management plan Timeline Budget Management structure Standard DoI response schedule Audits schedule provided at start up meeting Audits are carried out in accordance with the contract
Environmental Management Plan NTG and AG Audits Nominate Environment Manager Submit environment management plan Standard DoI response schedule Audits schedule provided at start up meeting Areas of concern include but not limited to Waste management Asbestos removal Gravel pits Sacred sites / graves
Tender Assessment Criteria and Weightings Past Performance 10% Timeliness 5% Capacity 10% Local Development 20% -Indigenous Development Plan Trade Apprentices 10% Community Risks 5% Industry Participation Plan 5% Quality Management Plan 5% Safety Management Plan 5% Environmental Management Plan 5% Price 20%
Preliminary Clauses Community Requirements Permits Cultural induction Contractor Accommodation Volatile Substances Community Engagement Transitional Tenant Accommodation Services to be provided by Contractor Light Power Water Sanitary Accommodation
Handover Requirements Handover Certification documents Department of Housing forms As constructed drawings, manuals and warranties Defects Dwelling handovers 52 weeks
Community Specific Community Engagement Roles and Responsibilities Department of Infrastructure Department of Housing Department of Families, Housing, Community Services and Indigenous Affairs Package Development Teams and Housing Reference Groups Scheduled Meetings Emergency Notifications Community Risks Risk matrix, contingency measures Time Communication Safety Environment Cultural
Innovation NPARIH is seeking innovation to allow the program to deliver out to 2018. Design must satisfy the design Guidelines and Performance Specifications. Building materials must provide a product fit for purpose for 30 years. Building Methodology must deliver on Indigenous Employment and Indigenous Business Participation wherever possible.
Other Housing Opportunities Government Employee Housing (GEH) and Public Housing Programs 88 DECS Houses AG funded over 4 years Gunbalanya/ Minjilang/ Palumpa/ Wurrimiyunga/ Alyangula/ BeswickBulman/ Kalkarindji/ Lajamanu/ Elliot/ Avon Downs/ Ali Curung/ Yuendumu/ Engawala Leases Innovation