An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. POCANTICO HILLS CENTRAL SCHOOL BOARD OF EDUCATIONSCHEMATIC DESIGN REPORTApril 29, 2008

  2. What have we been doing? • Meet every two weeks with stakeholders • Gathering of information related to program and overall room utilization • Generated several design solutions for each area, continued to review and redesigned accordingly • Provided information on products and systems for feedback • Onsite review, record review, and testing

  3. Design Schedule • Schematic Design…………………. April 2008 • Design Development…………….. June 2008 • Construction Documents….. October 2008

  4. Schedule

  5. Highlights, Gymnasium • Skylights • Bleachers • Replace lockers

  6. Highlights, Elevator • Access to two levels

  7. Highlights, Library • Centralized circulation desk • Visual of entire space • Two teaching stations • Increased collection • Seating areas • Server room

  8. Highlights, Principal/Nurse • Accessible bathroom • Separation of sick students • Better utilization of space

  9. Highlights, Guidance/Resource • Added space • Allowing for multiple uses • Accommodates many size groups • Computer stations

  10. Highlights, Science/Home Ec./Resource • Better utilization • Updated work stations

  11. Highlights, Technology • Central computer graphics lab • Visual lines from both areas • Kiln relocation • Integrated lift • Clean and dirty side to shop area

  12. Highlights, Swimming Pool • Updated filtration systems • Advanced chemical feeds • New perimeter gutter • Increased depth • Code compliant • Corrected deck

  13. Highlights, Roof • Modified bituminous material • Correction of drainage • Replace skylights • Replace gutters

  14. Highlights, HVAC • Conversion to hot water system • Single boiler room • New distribution • Ventilation • Air Conditioning • Potential geothermal

  15. Highlights, Electrical • Updated generator • Updated electric panels • Code compliant exit signs • New PA System • Solar power?