Lafayette Airport CommissionNew Terminal ProgramUpdate August 14, 2019
EDA Grant Application • $2M grant announced for long and short-term parking lots TSA OTA Application • Submitted Grant Application, unfunded in 2019 Airlines • Working with airlines to discuss leasable space and an agreement to buildout space QTA/Ready Return • Met with rental car agencies on construction progress to date. • Upcoming meetings regarding rates and charges Concessions Terminal ProgramUpdateFunding
Grant Funding Summary Terminal ProgramUpdateFunding
Rental Car Quick Turn Around Facility (QTA) Construction: • Notice to Proceed (NTP) 4/15/19; Scheduled Completion Q1 2020 • Upcoming Construction Activities • Plumbing rough-in, foundation slab and footings, electrical, retaining wall, curbing Terminal ProgramUpdateProjectsQTA
Rental Car Quick Turn Around Facility (QTA) Construction: Terminal ProgramUpdateProjectsQTA
New Terminal Program Progress: Day 1 Progress: Day 271
Project 2 – RTR Facility • Substantially complete – punch list items to be complete by 8/15 Project 2 RTR Facility
Project 3 – Terminal Building • Steel erection and steel decking – ongoing Project 3Terminal Building
Project 3 – Terminal Building Project 3Terminal Building Airside – Concourse Area
Project 5 – Enabling Parking • Substantially complete • Last punch list items complete – final acceptance upcoming Project 5 Enabling Parking
Project 6 – Terminal Site Civil • Underground utilities – ongoing • Loop Road - ongoing Project 5 Enabling Parking