430 likes | 445 Views
McClugage Bridge Rehabilitation. Contract Information:. Joint Venture between Midwest Foundation and Halverson Construction A+B Bidding Award Value - 26.1 Million 233 Days. Eastbound Structure. Peoria. East Peoria. Project Schedule:. March 13th - Close Eastbound Structure
E N D
Contract Information: • Joint Venture between Midwest Foundation and Halverson Construction • A+B Bidding • Award Value - 26.1 Million • 233 Days
Eastbound Structure Peoria East Peoria
ProjectSchedule: • March 13th - Close Eastbound Structure • November 1st - Re-Open Eastbound Structure • Incentive/Penalty - $25,000/Day • Work Hours - Two 10 Hour Shifts/6 Days Per Week
Traffic Facts: • ADT - 42,500 • Morning Rush Hour - 6:00 AM to 9:00 AM • Afternoon Rush Hour - 3:00 PM to 6:00 PM • Two Way Traffic on WB Structure
Public Relations Integrated into Design
Ensuring Public Relations Success: • Innovative Contracting • Innovative Traffic Management • Aggressive Public Relations Campaign
Innovative Traffic Management: • Moveable Barrier Wall • Automated Real-Time Traffic Control System • Video Surveillance Cameras
N IL 29 US 150/US 24 10:00 PM to 11:30 AM
N IL 29 US 150/US 24 11:30 AM TO 10:00 PM PM TRAFFIC CONTROL PATTERN Two Lanes Eastbound One Lane Westbound
AM Alignment - 10:00 PM to 11:30 AM 2.0’ 12’-4” 12’-4” 12’-4” WB TRAFFIC WB TRAFFIC EB TRAFFIC
PM Alignment - 11:30 AM to 10:00 PM 2.0’ 12’-4” 12’-4” 12’-4” WB TRAFFIC EB TRAFFIC EB TRAFFIC
Moveable Barrier Machine: • Weighs Approx. 16 Ton • Can Shift Barrier Wall From 4’ to 18’ • Approx. 5-10 MPH
Benefits of Moveable Barrier System: • Safety • Increase Capacity • Reduce Congestion • Good Public Relations