A PRESENTATION TO LOCAL GOVERNMENT BUDGET CONSULTATIVE WORKSHOPS FOR FY 2014/15 Strengthening the Procurement Function at the Local Government Level: Issues and Way Forward BY PPDA October 2013. HIGHLIGHTED ISSUES. Issues Raised in the Workshops of 2012/13
E N D
A PRESENTATION TO LOCAL GOVERNMENT BUDGET CONSULTATIVE WORKSHOPS FOR FY 2014/15 Strengthening the Procurement Function at the Local Government Level: Issues and Way ForwardBY PPDAOctober 2013
HIGHLIGHTED ISSUES • Issues Raised in the Workshops of 2012/13 • Force Account Method of Procurement. • Procurement Audit & Investigation Findings • New Procurement Plan Format • The Amended PPDA Law • Procurement Performance Measurement System (PPMS) • Tender Portal on PPDA Website
Force Account Method of Procurement. • PPPDA issued circular No. 3 of 2012, to all LG Accounting Officers to provide additional guidance on the use of Force Account mechanism. • This is to ease the use of road equipments that government has distributed to LGs to maintain roads in the districts (See Appendix A in the detailed paper).
Findings from Procurement Audit & Investigations • Procurement Fraud (Technical, Syndicate & intended crisis) • Conducting procurements outside the plan • Poor record keeping • Use of wrong methods of procurement • Forgery of documentation by the bidders • Not adhering to evaluation criteria in the Solicitation Document
Findings from Procurement Audit & Investigations Cont’d • Not extending bid validity which has led to the Authority directing the Entities to re-tender • Use of inappropriate evaluation methodologies • Awarding bids by the CC at Engineer's estimates leading to financial loss or shoddy work. • Poor contract management leading to shoddy work, incomplete works, and abandonment of sites or payment with no evidence of deliverables.
New Procurement Plan Format The new format provides details on: • the planed vs actual quantities, • basic data, • pre-qualification, • invitation for bids and evaluation; • contract finalization. This will enable PDEs track the progress of each procurement and ascertain where the delays are. (See Appendix B in the detailed paper)
The Amended PPDA Law A circular will soon be issued to brief LGs on the salient highlights of the amendments that equally apply to the LGs PDEs. Some key issues from amendments include: • Disposal of land under the District Land Board is not governed by the procedure for disposal under PPDA Act, 2003
The Amended PPDA Law Cont’d • A PDE will not enter into contract with: - A member of the CC, EC, employee of a PDE or member of the Board of Survey; and • A person appointed to politically or administratively control a PDE. • Suspension of Providers by the Authority on its own initiative
Procurement Performance Measurement System (PPMS) • PPDA rolled out PPMS to 105 Local and Central government PDEs by end of FY 2011/12 (29 of which are LGs see detailed paper). • PPMS will be used to assess the performance of LGs PDEs by the Authority • Also help in assessing the best performing LGs for award and recognition by PPDA at the end of each FY.
Tender Portal on PPDA Website • The tender portal on the PPDA website enables PDEs to post information relating to; tender opportunities, Best Evaluated Bidders, awarded contracts etc • LGs are highly encouraged to post their procurement and disposal opportunities on the tender portal since it’s a free of charge advertising media and for transparency purposes.