260 likes | 321 Views
ATF Operations Review. Budget Details and Baseline Projections Millie Wiener August 23, 2017. Contents – Needs updating. Overview of Funding and Expenditures Budget Assignments of Individuals M&S Breakdown Required Maintenance Emergency Maintenance Electricity and Consumables
E N D
ATF Operations Review Budget Details and Baseline Projections Millie Wiener August 23, 2017
Contents – Needs updating • Overview of Funding and Expenditures • Budget Assignments of Individuals • M&S Breakdown • Required Maintenance • Emergency Maintenance • Electricity and Consumables • Facility Upgrades • Overheads and Indirects • Space • Procurement Burden • Shop pricing
FY17 Funding and Expenditures HEP Ops and R&D have been fully funded in FY17 WFO expected funding of $24.8K from Radiabeam Carryover projected to be equivalent to last year however forward funding of $187K was received in Sept 2016 FY17 Ops + R&D == FY16 Ops
Effort Categorization in Requested Format • ATF Effort Categories • Facility Management • User Management • Upgrade Support • WE ADDED – Facility R&D
The NEW ATF Ops WBS • Historically there was only one account for ATF Operations • Accounts were added to collect cost for ATFII General Support and ATF II Laser Support • WBS Structure was implemented in January of FY17 • Over 20 activity accounts have been added • Greater level of project contol of budgets and cost • To implement quarterly status reports to manage labor and materials by WBS WBS Dictionary Eye Chart General Comments
ATF WBS: Operations Categories CO2 R&D
ATF WBS: ATF-II Support • ATF-II Planning and Oversight • ATF-II Laser • Supports Program Development
FY17 Budgets By WBS FY17 Budgets are 10 months of actuals 2 months estimated
FY17 Budget for ATF Operations Mgmt FY17 Budgets are 10 months of actuals 2 months estimated
FY17 Budget for Operations Categories FY17 Budgets are 10 months of actuals 2 months estimated
FY17 Budget for ATF-II Support FY17 Budgets are 10 months of actuals 2 months estimated Detailed Table Pie Chart
Labor and M&S Details by WBS FY17 Budgets are 10 months of actuals 2 months estimated Tables on left with small pie charts on right
FY18-20 Baseline Projections Extrapolate our effort from FY2017
Details of the new CAS - FY19 2019 BNL implements VAB accounting practices. BNL – C-AD Business OPS have provided the rates and burdens to estimate through 2020 Annual escalation is applied after 2020
Summary • Future Operations Accounting and Planning will be handled within the new ATF Ops WBS Structure • FY18-20 Projections are Baselines • New initiatives and identified needs are covered in Session 4 • These imply adjustments to the baseline budgets